Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Jun 2023 |
Pack-1
Work in progress | 90% Completed | 02/06/2023
Railway crossing work in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work in progress
Pack-2
Not Started | 02/06/2023
work retendered
pack-3
Work in progress | 93% Completed | 02/06/2023
Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
Pack-4
Not Started | 02/06/2023
retender procedure processing
pack-5
work foreclosed
|
Chittur Project Dn - AE 2 |
|
26 May 2023 |
Pack-1
Work in progress | 75% Completed | 26/05/2023
Railway crossing work in progress,Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work in progress
Pack-2
Not Started | 26/05/2023
work retendered
pack-3
Work in progress | 93% Completed | 26/05/2023
Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
Pack-4
Not Started | 26/05/2023
retender procedure processing
|
Chittur Project Dn - AE 2 |
|
19 May 2023 |
Pack-1
Work in progress | 75% Completed | 19/05/2023
Railway crossing work started.Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work in progress
Pack-2
Not Started | 19/05/2023
retender work in progress
pack-3
Work in progress | 93% Completed | 19/05/2023
Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
Pack-4
Not Started | 19/05/2023
retender procedure processing
|
Chittur Project Dn - AE 2 |
|
11 May 2023 |
Pack-1
Work in progress | 72% Completed | 11/05/2023
Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work in progress
Pack-2
Not Started | 11/05/2023
retendering procedure processing
pack-3
Work in progress | 92% Completed | 11/05/2023
Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
Pack-4
Not Started | 11/05/2023
retender procedure processing
|
Chittur Project Dn - AE 2 |
|
05 May 2023 |
Pack-1
Work in progress | 72% Completed | 05/05/2023
Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – white washing work in progress at Malampuzha 3). 7LL OHSR— OHSR white washing work is in progress at Padalikkad 4) Malampuzha pump house – white washing work in progress 5) 350 mm DI K9 common CWPM pipe - 5700 M pipe supplied and 5700.00 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.961km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR – 38.50M Laid 8) padalikkad bridge-pier and tie beam work completed and steel fabrication work in progress
Pack-2
Not Started | 05/05/2023
tender procedure processing ,last date of tender acceptance-10.05.2023
pack-3
Work in progress | 92% Completed | 05/05/2023
Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
Pack-4
Not Started | 05/05/2023
Tender procedure processing-last date of tender acceptance-06.05.2023
Pack-5
Fore closed the work
|
Chittur Project Dn - AE 2 |
|
28 Apr 2023 |
pack-1
Work in progress | 72% Completed | 28/04/2023
Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – OHSR outside plastering work complete except inside plastering at Malampuzha 3). 7LL OHSR— OHSR outside plastering work complete except inside plastering completed at Padalikkad 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed
Pack-2
Not Started | 28/04/2023
tender procedure processing ,last date of tender acceptance-10.05.2023
pack-3
Work in progress | 91% Completed | 28/04/2023
Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
Pack-4
Not Started | 28/04/2023
Tender procedure processing-last date of tender acceptance-06.05.2023
Pack-5
Work in progress | 97% Completed | 28/04/2023
THE WORK IS FORE CLOSED
|
Chittur Project Dn - AE 2 |
|
21 Apr 2023 |
PACK-1
Work in progress | 71% Completed | 21/04/2023
Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – OHSR outside plastering work complete except inside plastering at Malampuzha 3). 7LL OHSR— OHSR outside plastering work complete except inside plastering completed at Padalikkad 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed
PACK-2
Not Started | 21/04/2023
Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023
PACK-3
Work in progress | 91% Completed | 21/04/2023
Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
PACK-4
Not Started | 21/04/2023
Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023
PACK-5
Work in progress | 97% Completed | 21/04/2023
THE WORK IS FORE CLOSED
|
Chittur Project Dn - AE 2 |
|
10 Apr 2023 |
PACK-1
Work in progress | 71% Completed | 10/04/2023
Trial run of pumping main towards 8LL OHSR Malampuzha from Malampuzha pump house 1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – OHSR outside plastering work complete except inside plastering at Malampuzha 3). 7LL OHSR— OHSR outside plastering work complete except inside plastering completed at Padalikkad 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed
PACK-2
Not Started | 10/04/2023
Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023
PACK-3
Work in progress | 91% Completed | 10/04/2023
Total pipe 17.794 km supplied at site and 17.480 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 13161.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
PACK-4
Not Started | 10/04/2023
Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023
PACK-5
Work in progress | 97% Completed | 10/04/2023
THE WORK IS FORE CLOSED
|
Chittur Project Dn - AE 2 |
|
04 Apr 2023 |
Pack-1
Work in progress | 71% Completed | 04/04/2023
1) 11 LL OHSR at JTS – cover slab and beam concrete work completed at JTS Marutharoad 2). 8 LL OHSR – OHSR outside plastering work complete except inside plastering at Malampuzha 3). 7LL OHSR— OHSR outside plastering work complete except inside plastering completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed
Pack-2
Not Started | 04/04/2023
Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023
Pack-3
Work in progress | 91% Completed
Total pipe 17.794 km supplied at site and 17.119 km laid 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed,hand rail work completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab concrete work completed 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed , hand rail work completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 12800.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2858.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
PACK-4
Not Started | 04/04/2023
Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023
PACK-5
Work in progress | 97% Completed | 04/04/2023
tHE WORK IS FORE CLOSED
|
Chittur Project Dn - AE 2 |
|
24 Mar 2023 |
PACK-1
Work in progress | 71% Completed | 24/03/2023
1) 11 LL OHSR at JTS – cover slab and beam reinforcement work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed
PACK-2
Work in progress | 3% Completed | 24/03/2023
Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023
Pack-3
Work in progress | 91% Completed | 24/03/2023
1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Coverslab shuttering work in proressing 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
Pack-4
Not Started | 24/03/2023
Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-
pack-5
The work is foreclosed
|
Chittur Project Dn - AE 2 |
|