Status Date |
Overall Project Status |
Project Officer |
Contact |
11 May 2022 |
Pack-1
Work in progress | 45% Completed | 11/05/2022
1) 11 LL OHSR at JTS – floor slab shuttering work started at JTS Marutharoad 2). 8 LL OHSR – 3rd lift concrete work and Inner column concrete work in progress at Malampuzha 3). 7LL OHSR— floor slab shuttering work is in progress at Padalikkad 4) Malampuzha pump house- roof slab shuttering work in progress, 5) 350 mm DI K9 pipe - 4747 M pipe supplied and 1.00km m laid 6) 300mm DI pipe –from padalikkad to JTS-2 km supplied and 1.80km laid 7) padalikkad bridge-river crossing work-pier work in progress
Pack-2
Not Started | 11/05/2022
Revised Estimate under preparation (as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 24.02.2022)
Pack-3
Work in progress | 73% Completed | 11/05/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – first brace work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection in progress 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara
Pack-4
Work in progress | 22% Completed | 11/05/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 and 24.02.2022
Pack-5
Work in progress | 96% Completed | 11/05/2022
LINKING work in progress 1.) 90mm pvc,6kg/cm2 – 73044 M 2)110mm pvc,6kg/cm2 – 2734m 3) 140mm pvc,6kg/cm2 – 3841 m 4)160mm pvc,6kg/cm2 - 2129 m 5)200mm DI K9 – 2814 m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km
|
Chittur Project Dn - AE 2 |
|
02 May 2022 |
Pack-1
Work in progress | 45% Completed | 02/05/2022
Pack-1 1) 11 LL OHSR at JTS – floor slab shuttering work to be done at JTS Marutharoad 2). 8LL OHSR – sidewall second lift shuttering and reinforcement work and Inner column concrete work in progress at Malampuzha 3). 7LL OHSR— floor slab shuttering work is in progress at Padalikkad 4) Malampuzha pump house- roof slab shuttering work in progress, 5) 350 mm DI K9 pipe - 4747 M pipe supplied and 1.00km m laid 6) 300mm DI pipe –from padalikkad to JTS-2 km supplied and 1.80km laid
Pack-2
Not Started | 02/05/2022
Revised Estimate under preparation (as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 24.02.2022)
PACK-3
Work in progress | 73% Completed | 02/05/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – first brace shuttering work in progress 3.) 11.50 LL OHSR -Cherad OHSR- cover slab concrete work completed and floor slab plastering work and vertical column pipe erection in progress 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 10853.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2058.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1200.00 m laid to akathethara
PACK-4
Work in progress | 22% Completed | 02/05/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 and 24.02.2022
PACK-5
Work in progress | 96% Completed | 02/05/2022
LINKING work in progress 1.) 90mm pvc,6kg/cm2 – 73033M 2)110mm pvc,6kg/cm2 – 2390m 3) 140mm pvc,6kg/cm2 – 3832 m 4)160mm pvc,6kg/cm2 - 2062 m 5)200mm DI K9 - 2632m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 94.566km
|
Chittur Project Dn - AE 2 |
|
25 Apr 2022 |
sd/-
Executive Engineer
Pack-1
Work in progress | 43% Completed | 25/04/2022
Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam up to floor slab work completed at JTS Marutharoad 2). 8LL OHSR - Side wall first lift concrete work in progress at Malampuzha 3). 7LL OHSR— Columns second lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- shuttering work for lintel work in progress , 5)350 mm DI K9 pipe - 4747 M pipe supplied and 1.00km m laid 6) 300mm DI pipe –from padalikkad to JTS-2 km supplied and 1.80km laid
Pack-2
Not Started | 25/04/2022
Revised Estimate under preparation (as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 24.02.2022)
Pack-3
Work in progress | 72% Completed | 25/04/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – first brace shuttering work in progress 3.) 11.50 LL OHSR -Cherad OHSR- cover slab concrete work completed and floor slab plastering work in progress 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 10853.00m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2058.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1200.00 m laid to akathethara
Pack-4
Work in progress | 22% Completed | 25/04/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 and 24.02.2022
Pack-5
Work in progress | 96% Completed | 25/04/2022
LINKING work in progress 1.) 90mm pvc,6kg/cm2 – 73033M 2)110mm pvc,6kg/cm2 – 2390m 3) 140mm pvc,6kg/cm2 – 3832 m 4)160mm pvc,6kg/cm2 - 2062 m 5)200mm DI K9 - 2632m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 94.566km
|
Chittur Project Dn - AE 2 |
|
18 Apr 2022 |
Pack-1
Work in progress | 43% Completed | 18/04/2022
Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam up to floor slab work completed at JTS Marutharoad 2). 8LL OHSR - Floor slab and beam concrete work complete Malampuzha 3). 7LL OHSR— Columns second lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- plinth beam work completed , 5)350 mm DI K9 pipe - 4747 M pipe supplied and 1.00km m laid 6) 300mm DI pipe –from padalikkad to JTS-2 km supplied and 1.80km laid
Pack-2
Not Started | 18/04/2022
Revised Estimate under preparation (as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 24.02.2022)
Pack-3
Work in progress | 72% Completed | 18/04/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – first brace shuttering work in progress 3.) 11.50 LL OHSR -Cherad OHSR- cover slab concrete work completed and floor slab plastering work in progress 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 10853.00m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2058.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1200.00 m laid to akathethara
Pack-4
Work in progress | 22% Completed | 18/04/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 and 24.02.2022
Pack-5
Work in progress | 96% Completed | 18/04/2022
LINKING work in progress 1.) 90mm pvc,6kg/cm2 – 73033M 2)110mm pvc,6kg/cm2 – 2390m 3) 140mm pvc,6kg/cm2 – 3832 m 4)160mm pvc,6kg/cm2 - 2062 m 5)200mm DI K9 - 2632m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 94.566km
|
Chittur Project Dn - AE 2 |
|
12 Apr 2022 |
Pack-1
Work in progress | 43% Completed
Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam up to floor slab work completed at JTS Marutharoad 2). 8LL OHSR - Floor slab and beam concrete work complete Malampuzha 3). 7LL OHSR— Columns second lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- plinth beam work completed , 5)350 mm DI K9 pipe - 4747 M pipe supplied and 1.00km m laid 6) 300mm DI pipe –from padalikkad to JTS-2 km supplied and 1.80km laid
Pack-2
Not Started | 12/04/2022
Revised Estimate under preparation (as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 24.02.2022)
pack-3
Work in progress | 71% Completed | 12/04/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – first brace shuttering work in progress 3.) 11.50 LL OHSR -Cherad OHSR- cover slab concrete work completed and floor slab plastering work in progress 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 10853.00m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2058.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1200.00 m laid to akathethara
Pack-4
Not Started | 12/04/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 and 24.02.2022
Pack-5
Work in progress | 95% Completed | 12/04/2022
LINKING work in progress 1.) 90mm pvc,6kg/cm2 – 73033M 2)110mm pvc,6kg/cm2 – 2390m 3) 140mm pvc,6kg/cm2 – 3832 m 4)160mm pvc,6kg/cm2 - 2062 m 5)200mm DI K9 - 2632m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 94.566km
|
Chittur Project Dn - AE 2 |
|
06 Apr 2022 |
Pack-1
Work in progress | 43% Completed | 06/04/2022
Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam up to floor slab work completed at JTS Marutharoad 2). 8LL OHSR - Floor slab and beam concrete work complete Malampuzha 3). 7LL OHSR— Columns second lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- plinth beam work completed , 5)350 mm DI K9 pipe - 4747 M pipe supplied and 1.00km m laid 6) 300mm DI pipe –from padalikkad to JTS-2 km supplied and 1.80km laid
Pack-2
Not Started | 06/04/2022
Revised Estimate under preparation (as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 24.02.2022)
Pack-4
Not Started | 06/04/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 and 24.02.2022
Pack-3
Work in progress | 71% Completed | 06/04/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- cover slab concrete work completed and floor slab plastering work in progress 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 10853.00m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2058.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1200.00 m laid to akathethara
Pack-5
Work in progress | 95% Completed | 06/04/2022
LINKING work in progress 1.) 90mm pvc,6kg/cm2 – 73033M 2)110mm pvc,6kg/cm2 – 2390m 3) 140mm pvc,6kg/cm2 – 3832 m 4)160mm pvc,6kg/cm2 - 2062 m 5)200mm DI K9 - 2632m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 94.566km
|
Chittur Project Dn - AE 2 |
|
30 Mar 2022 |
Pack-1
Work in progress | 42% Completed | 30/03/2022
Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam concrete work in progress at JTS Marutharoad 2). 8LL OHSR - Floor slab and beam concrete work complete Malampuzha 3). 7LL OHSR— Columns second lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- column footings completed OHSR at padalikkad, 5)350 mm DI K9 pipe - 4747 M pipe supplied and 1.00km m laid 6) 300mm DI pipe –from padalikkad to JTS-2 km supplied and 1.80km laid
Pack-2
Not Started | 30/03/2022
Revised Estimate under preparation (as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 24.02.2022)
Pack-4
Work in progress | 22% Completed | 30/03/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021 and 24.02.2022
Pack-3
Work in progress | 71% Completed | 30/03/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- cover slab form work in progress, floor slab plastering work in progress 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and -9500m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 1946.80 m laid 7).250mm DI K9pipe-1254.00m supplied and 1200.00 m laid to akathethara
Pack-5
Work in progress | 95% Completed | 30/03/2022
Work in progress | 95% Completed | 24/03/2022 1.) 90mm pvc,6kg/cm2 – 73033M 2)110mm pvc,6kg/cm2 – 2390m 3) 140mm pvc,6kg/cm2 – 3832 m 4)160mm pvc,6kg/cm2 - 2062 m 5)200mm DI K9 - 2632m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 94.566km
|
Chittur Project Dn - AE 2 |
|
23 Mar 2022 |
Pack-1
Work in progress | 40% Completed | 23/03/2022
Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam casting work in progress at JTS Marutharoad 2). 8LL OHSR - Floor slab shuttering work progress at Malampuzha 3). 7LL OHSR— Columns second lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- column footings completed OHSR at padalikkad, 5)350 mm DI K9 pipe - 4747 M pipe supplied and 1.00km m laid 6) 300mm DI pipe -2 km supplied pumping main laying work in progress at Padalikkad-1.2km laid
Pack-2
Not Started | 23/03/2022
It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date
Pack-3
Work in progress | 70% Completed | 23/03/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall third lift shuttering work in progress 4) .Pumping main -400 mm DI K9 pipe- 13255supplied and -9000.00m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 1946.80 m laid 7).250mm DI K9pipe-1254.00m supplied and 1130.00 m laid to akathethara
Pack-4
Work in progress | 22% Completed | 23/03/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021
Pack-5
Work in progress | 94% Completed | 23/03/2022
1.) 90mm pvc,6kg/cm2 – 73009M 2)110mm pvc,6kg/cm2 – 2102m 3) 140mm pvc,6kg/cm2 – 3334 m 4)160mm pvc,6kg/cm2 - 1972 m 5)200mm DI K9 - 2368m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 93.402km
|
Chittur Project Dn - AE 2 |
|
17 Mar 2022 |
Pack-1
Work in progress | 40% Completed | 17/03/2022
Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam casting work in progress at JTS Marutharoad 2). 8LL OHSR - Floor slab shuttering work progress at Malampuzha 3). 7LL OHSR— Columns first lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- column footings completed OHSR at padalikkad, 5)350 mm DI K9 pipe - 4747 M pipe supplied and 800 m laid 6) 300mm DI pipe -2 km supplied pumping main laying work in progress at Padalikkad-1000m laid
Pack-5
Work in progress | 93% Completed | 17/03/2022
1.) 90mm pvc,6kg/cm2 – 73009M 2)110mm pvc,6kg/cm2 – 2102m 3) 140mm pvc,6kg/cm2 – 3334 m 4)160mm pvc,6kg/cm2 - 1972 m 5)200mm DI K9 - 2368m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 93.402km
|
Chittur Project Dn - AE 2 |
|
16 Mar 2022 |
Pack-1
Work in progress | 38% Completed | 16/03/2022
Pack-1 1) 11 LL OHSR at JTS – Columns and stair above 4th brace beam casting work in progress at JTS Marutharoad2). 8LL OHSR - Floor slab shuttering work progress at Malampuzha 3). 7LL OHSR— Columns first lift concrete work above 4th brace work is in progress at Padalikkad 4) Malampuzha pump house- column footings completed OHSR at padalikkad, 4)350 mm DI K9 pipe - 4747 M pipe supplied and 800 m laid 5) 300mm DI pipe pumping main laying work in progress at Padalikkad-900m laid
Pack-2
Not Started | 16/03/2022
It was decided in the meeting held in the chamber of Hon.Minister on 02.11.2021 to take final decision regarding the execution or cancellation of the work ,after detailed discussion on a later date
Pack-3
Work in progress | 68% Completed | 16/03/2022
1) 8LL OHSR-Mundur –plastering work completed (2) 20LL OHSR – column up to first brace work complete 3.) 11.50 LL OHSR -Cherad OHSR- side wall third lift shuttering work in progress 4) .Pumping main -400 mm DI K9 pipe- 13255supplied and -9000.00m laid . 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 1946.80 m laid 7).250mm DI K9pipe-1254.00m supplied and 1130.00 m laid to akathethara
Pack-4
Work in progress | 22% Completed | 16/03/2022
Revised Estimate prepared and submitted for exploring the possibility for approval of price escalation from KIIFB as per the direction taken in the meeting held in the chamber of Hon. water resources Minister on 02.11.2021
Pack-5
Work in progress | 93% Completed | 16/03/2022
supplied qty 80MM GI pipe-378 m ,125 mm GI -42m , 150mm GI-36M ,(PIPE LAID ) 1.) 90mm pvc,6kg/cm2 – 72994.00M 2)110mm pvc,6kg/cm2 – 2080 m 3) 140mm pvc,6kg/cm2 – 3178 m 4)160mm pvc,6kg/cm2 - 1590 m 5)200mm DI K9 - 2368m 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-224m 11)125mm GI-30m 12)150mm GI 30m TOTAL – 93.402km
|
Chittur Project Dn - AE 2 |
|