Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Mar 2023 Pack-1 Work in progress | 71% Completed | 13/03/2023 1) 11 LL OHSR at JTS – cover slab and beam reinforcement work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2 Work not started | | 13/03/2023 Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023 Pack-3 Work in progress | 91% Completed | 13/03/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall THIRD lift Concrete work completed. inside column work proressing 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 13/03/2023 Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023 Pack-5 Work in progress | 100% Completed | 13/03/2023 The work completed Chittur Project Dn - AE 2
05 Mar 2023 pack-1 Work in progress | 70% Completed | 05/03/2023 1) 11 LL OHSR at JTS – cover slab and beam reinforcement work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed PACK-2 Not Started | 05/03/2023 Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023 PACK-4 Not Started | 05/03/2023 Revised estimate SANCTION approved wide order no.KWA/JB/PIU-2/AEE-5/KIIFB/Malampuzha-pk-IV/2021 ON 28.02.2023 PACK-3 Work in progress | 91% Completed | 05/03/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall THIRD lift Concrete work completed. inside column work proressing 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara PACK-5 Not Started | 05/03/2023 The work is foreclosed Chittur Project Dn - AE 2
24 Feb 2023 PACK-1 Work in progress | 69% Completed | 24/02/2023 1) 11 LL OHSR at JTS – sidewall third lift concrete work complete at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed PACK-2 Not Started | 24/02/2023 Revised estimate submitted Pack-3 Work in progress | 91% Completed | 24/02/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall second lift Concrete work completed. inside column work proressing 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Revised estimate submitted Pack-5 Work in progress | 97% Completed | 24/02/2023 The work is foreclosed Chittur Project Dn - AE 2
17 Feb 2023 Pack-1 Work in progress | 69% Completed | 17/02/2023 1) 11 LL OHSR at JTS – sidewall third lift concrete work complete at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-3 Work in progress | 91% Completed | 17/02/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall second lift reinforcement and shuttering work in progress3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-2 Not Started | 17/02/2023 Revised estimate submitted Pack-4 Not Started | 17/02/2023 Revised estimate submitted Pack-5 Work in progress | 97% Completed | 17/02/2023 The work is foreclosed Chittur Project Dn - AE 2
10 Feb 2023 pack-1 Work in progress | 68% Completed | 10/02/2023 1) 11 LL OHSR at JTS – sidewall third lift concrete work complete at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2 Not Started | 10/02/2023 Revised estimate submitted Pack-3 Work in progress | 91% Completed | 10/02/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall first lift concrete work complete second lift reinforcement and shuttering work in progress3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 10/02/2023 Revised estimate submitted Pack-5 Work in progress | 97% Completed | 10/02/2023 The work is foreclosed Chittur Project Dn - AE 2
03 Feb 2023 Pack-1 Work in progress | 68% Completed | 03/02/2023 1) 11 LL OHSR at JTS – sidewall third lift concrete work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2 Not Started | 03/02/2023 Revised estimate submitted pack-3 Work in progress | 91% Completed | 03/02/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall first lift concrete work complete second lift reinforcement and shuttering work in progress3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 03/02/2023 Revised estimate submitted Pack-5 Foreclosed the work Chittur Project Dn - AE 2
30 Jan 2023 Pack-1 Work in progress | 66% Completed | 30/01/2023 1) 11 LL OHSR at JTS – sidewall third lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house - plastering, Brick work, motor and pump set fixing ,fabrication work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4150 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2 Not Started | 30/01/2023 Revised estimate submitted Pack-3 Work in progress | 90% Completed | 30/01/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall first lift concrete work complete 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 30/01/2023 Revised estimate submitted Pack-5 Work in progress | 97% Completed | 30/01/2023 The work is foreclosed Chittur Project Dn - AE 2
20 Jan 2023 Pack-1 Work in progress | 66% Completed | 20/01/2023 1) 11 LL OHSR at JTS – sidewall second lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall outside plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house- plastering work and motor work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4000 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed 9) pump house- inside plastering work and parapet wall brick work also in progress Pack-2 Not Started | 20/01/2023 Revised estimate submitted Pack-3 Work in progress | 90% Completed | 20/01/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- sidewall first lift concrete work complete 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara 2) Pack-4 Not Started | 20/01/2023 Revised estimate submitted Pack-5 Work in progress | 97% Completed | 20/01/2023 The work is foreclosed Chittur Project Dn - AE 2
13 Jan 2023 Pack-1 Work in progress | 66% Completed | 13/01/2023 1) 11 LL OHSR at JTS – sidewall second lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall outside plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house- plastering work and motor work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4000 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed 9) pump house- inside plastering work and parapet wall brick work also in progress Pack-3 Work in progress | 90% Completed | 13/01/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- floor beam concrete work complete 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-2 Not Started -13/01/2023-Revised estimate submitted Pack-4 Not Started | 13/01/2023 Revised estimate submitted Pack-5 Work in progress | 97% Completed | 06/01/2023 The work is foreclosed Chittur Project Dn - AE 2
06 Jan 2023 Pack-1 Work in progress | 66% Completed | 06/01/2023 1) 11 LL OHSR at JTS – sidewall second lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall outside plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house- plastering work and motor work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4000 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed 9) pump house- inside plastering work in progress Pack-2 Not Started | 30/12/2022 Revised estimate submitted Pack-3 Work in progress | 90% Completed | 06/01/2023 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- floor beam reinforcement work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 06/01/2023 Revised estimate submitted Pack-5 Work in progress | 97% Completed | 06/01/2023 The work is foreclosed Chittur Project Dn - AE 2