Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Dec 2022 Pack-1 Work in progress | 66% Completed | 30/12/2022 1) 11 LL OHSR at JTS – sidewall second lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall outside plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab concrete work completed at Padalikkad – 4) Malampuzha pump house- plastering work and motor work in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4000 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed 9) pump house- inside plastering work in progress Pack-2 Not Started | 30/12/2022 Revised estimate submitted Pack-3 Work in progress | 90% Completed | 30/12/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- floor beam reinforcement work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 30/12/2022 Revised estimate submitted PACK-5 Work in progress | 97% Completed | 30/12/2022 The work is foreclosed herewith and the work through NH portion is not to be executed as part of this agreement . Chittur Project Dn - AE 2
22 Dec 2022 Pack-1 Work in progress | 66% Completed | 22/12/2022 1) 11 LL OHSR at JTS – sidewall second lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall outside plastering work progressing at Malampuzha 3). 7LL OHSR— Cover slab shuttering and reinforcement work in progressing Padalikkad – 4) Malampuzha pump house- solid block masonry work for side wall in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4000 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed 9) pump house- inside plastering work in progress Pack-2 Not Started | 22/12/2022 Revised estimate under preparation Pack-3 Work in progress | 90% Completed | 22/12/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- floor beam shuttering work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Not Started | 22/12/2022 revised estimate under preparation pack-5 the work foreclosed order issued by SE PH CIRCLE ,Palakkad wide order no. KWA/PHC/PKD/KIIFB-MPZ/PACK-V/17-18 DATED 24.08.2022 Chittur Project Dn - AE 2
16 Dec 2022 Pack-1 Work in progress | 65% Completed | 16/12/2022 1) 11 LL OHSR at JTS – sidewall first lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall outside plastering work progressing at Malampuzha 3). 7LL OHSR— side wall third lift shuttering and reinforcement work in progressing Padalikkad – 4) Malampuzha pump house- solid block masonry work for side wall in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 4000 m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.500km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2 Not Started | 16/12/2022 Revised estimate under preparation Pack-3 Work in progress | 90% Completed | 16/12/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- floor beam shuttering work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 23% Completed | 16/12/2022 revised estimate under preparation pack-5 Work in progress | 97% Completed | 16/12/2022 Road side concrete work in progress,valve chamber work completed linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
02 Dec 2022 Pack-1 Work in progress | 65% Completed | 02/12/2022 1) 11 LL OHSR at JTS – sidewall first lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall outside plastering work progressing at Malampuzha 3). 7LL OHSR— side wall third lift shuttering and reinforcement work in progressing Padalikkad – 4) Malampuzha pump house- solid block masonry work for side wall in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.300km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2 Not Started | 02/12/2022 As per the decision of meeting held on 26.10.2022 in the chamber of Hon`ble WRD minister has instructed to KWA for the cancellation of the existing work without risk and cost of the contractor in package-II and Package -IV . Then recall the new tender that based on new SOR.Superintending Engineer has directed to prepare and submit realistic working estimate wide e -mail message as on 21.11.2022. As per the proceedings of the superintending engineer the work foreclosed order was issued on 30.11.2022 Pack-3 Work in progress | 89% Completed | 02/12/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Column above fourth brace second lift concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 23% Completed | 02/12/2022 work foreclosed:-As per the decision of meeting held on 26.10.2022 in the chamber of Hon`ble WRD minister has instructed to KWA for the cancellation of the existing work without risk and cost of the contractor in package-II and Package -IV . Then recall the new tender that based on new SOR.Superintending Engineer has directed to prepare and submit realistic working estimate wide e -mail message as on 21.11.2022. As per the proceedings of the superintending engineer the work foreclosed order was issued on 30.11.2022 pack-5 Work in progress | 97% Completed | 02/12/2022 Road side concrete work in progress,valve chamber work completed linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
25 Nov 2022 Pack-1 Work in progress | 65% Completed | 25/11/2022 1) 11 LL OHSR at JTS – sidewall first lift shuttering and reinforcement work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – OHSR sidewall outside plastering work progressing at Malampuzha 3). 7LL OHSR— side wall third lift shuttering and reinforcement work in progressing Padalikkad – 4) Malampuzha pump house- solid block masonry work for side wall in progress 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 3.300km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2 Not Started | 25/11/2022 As per the decision of meeting held on 26.10.2022 in the chamber of Hon`ble WRD minister has instructed to KWA for the cancellation of the existing work without risk and cost of the contractor in package-II and Package -IV .Then recall the new tender that based on new SOR.Superintending Engineer has directed to prepare and submit realistic working estimate wide e -mail message as on 21.11.2022. Pack-3 Work in progress | 89% Completed | 25/11/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Column above fourth brace second lift concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 23% Completed | 25/11/2022 As per the decision of meeting held on 26.10.2022 in the chamber of Hon`ble WRD minister has instructed to KWA for the cancellation of the existing work without risk and cost of the contractor in package-II and Package -IV .Then recall the new tender that based on new SOR.Superintending Engineer has directed to prepare and submit realistic working estimate wide e -mail message as on 21.11.2022. Chittur Project Dn - AE 2
10 Nov 2022 Pack-1 Work in progress | 64% Completed | 09/11/2022 1) 11 LL OHSR at JTS – internal column work and Haunch concreting work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – plastering work and hand rail work progressing at Malampuzha 3). 7LL OHSR— side wall first lift shuttering work and plastering work also progressing Padalikkad – 4) Malampuzha pump house- roof slab concrete work completed, 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed PACK-2 FORECLOSED | 10/11/2022 Based on the decision of the meeting in the chamber of hon: minister of Water Resource Department on 26.10.2022.Minister has instructed to KWA for the cancillation of the existing work without risk and cost of the contractor in package-II and Package -IV .Then recall the new tender that based on new SOR. Pack-3 Work in progress | 88% Completed | 10/11/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- Column above fourth brace second lift concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 23% Completed | 10/11/2022 FORECLOSED | 10/11/2022 Based on the decision of the meeting in the chamber of hon: minister of Water Resource Department on 26.10.2022.Minister has instructed to KWA for the cancillation of the existing work without risk and cost of the contractor in package-II and Package -IV .Then recall the new tender that based on new SOR. Chittur Project Dn - AE 2
28 Oct 2022 Pack-1 Work in progress | 62% Completed | 28/10/2022 1) 11 LL OHSR at JTS – Haunch shuttering work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – plastering work and hand rail work progressing at Malampuzha 3). 7LL OHSR— side wall first lift shuttering work and plastering work also progressing Padalikkad – 4) Malampuzha pump house- roof slab concrete work completed, 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2-Not Started | 28/10/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superintending Engineer directed the contractor to start the work , and a detailed report submitted to TM through SE about this work,repoprt attached here with Pack-3 Work in progress | 87% Completed | 28/10/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- fourth brace concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 23% Completed | 28/10/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Chittur Project Dn - AE 2
20 Oct 2022 Pack-1 Work in progress | 62% Completed | 20/10/2022 1) 11 LL OHSR at JTS – Haunch shuttering work and plastering work in progress at JTS Marutharoad 2). 8 LL OHSR – plastering work and hand rail work progressing at Malampuzha 3). 7LL OHSR— side wall first lift shuttering work and plastering work also progressing Padalikkad – 4) Malampuzha pump house- roof slab concrete work completed, 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-pier F1 TO F7 Partially fabrication work completed Pack-2 Not Started | 20/10/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superintending Engineer directed the contractor to start the work , and a detailed report submitted to TM through SE about this work,repoprt attached here with Pack-3 Work in progress | 87% Completed | 20/10/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- fourth brace concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 20/10/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 97% Completed | 20/10/2022 Road side concrete work in progress,valve chamber work completed linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
14 Oct 2022 Pack-1 Work in progress | 59% Completed | 14/10/2022 1) 11 LL OHSR at JTS – Haunch shuttering work in progress at JTS Marutharoad 2). 8 LL OHSR – plastering work and hand rail work progressing at Malampuzha 3). 7LL OHSR— Haunch shuttering work in progress at Padalikkad – plastering work also progressing 4) Malampuzha pump house- roof slab shuttering and reinforcement work in progress, 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-steel fabrication work in progress Pack-2 Not Started | 14/10/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superintending Engineer directed the contractor to start the work Pack-3 Work in progress | 85% Completed | 14/10/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- column above third brace concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 14/10/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 97% Completed | 14/10/2022 Road side concrete work in progress,valve chamber work completed linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2
08 Oct 2022 Pack-1 Work in progress | 59% Completed | 08/10/2022 1) 11 LL OHSR at JTS – Haunch shuttering work in progress at JTS Marutharoad 2). 8 LL OHSR – coverslab concrete work completed and plastering work progressing at Malampuzha – 3). 7LL OHSR— Haunch shuttering work in progress at Padalikkad – plastering work also progressing 4) Malampuzha pump house- roof slab shuttering and reinforcement work in progress, 5) 350 mm DI K9 common CWPM pipe - 4747 M pipe supplied and 3811 km m laid – 6) 300mm DI CWPM pipe –from padalikkad jn. to JTS OHSR -4 km supplied and 2.60km laid 7) 200mm DI CWPM pipe from Padalikkad jn to Padalikkad OHSR - Not started 8) padalikkad bridge-steel fabrication work in progress Pack-2 Not Started | 08/10/2022 Technical sanction for the revised estimate is obtained from CE, kozhikode and Superintending Engineer directed the contractor to start the work Pack-3 Work in progress | 85% Completed | 08/10/2022 1) 8LL OHSR- Mundur – plastering work completed vertical column pipe erection completed (2) 20LL OHSR –puthupperiyaram -valayakkad- column above third brace concrete work in progress 3.) 11.50 LL OHSR -Cherad OHSR- plastering work and vertical column pipe erection completed 4) .Pumping main - 400 mm DI K9 pipe- 13255supplied and – 11353.00m laid. 5)350mm DI K9-308.90m supplied and 225.00m laid 6).250mm DI K9 -2975.50M supplied 2458.30 m laid 7).250mm DI K9pipe-1254.00m supplied and 1236.00 m laid to akathethara Pack-4 Work in progress | 22% Completed | 08/10/2022 Revised estimate had been submitted to KIIFB for approval. KIIFB directed to take decision by agreement authority and to direct contractor to carryout the work as per present contract Pack-5 Work in progress | 97% Completed | 08/10/2022 Road side concrete work in progress,valve chamber work completed linking work also completed 1.) 90mm pvc,6kg/cm2 – 73044 M . 2)110mm pvc,6kg/cm2 – 2734m . 3) 140mm pvc,6kg/cm2 – 3841 m . 4)160mm pvc,6kg/cm2 - 2129 m. 5)200mm DI K9 – 2814 m . 6)250mm DI K9 - 999 m 7) 300mm DI K9 – 471.00m . 8)350mm DI K9 – 649.50m 9) 400mm DI K9 - 247m 10) 80 mm GI-366m 11)125mm GI-36m 12)150mm GI 36m TOTAL – 95.335km Chittur Project Dn - AE 2