Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Jan 2022 | 3935 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
13 Jan 2022 | 3910 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
10 Jan 2022 | 3910 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
06 Jan 2022 | 3887 Nos FHTCS provided. 42 km pipe line extended. Physical progress 77%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
02 Jan 2022 | 3877 Nos FHTCS provided. 42 km pipe line extended. Physical progress 77%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
29 Dec 2021 | 3877 Nos FHTCS provided. 42 km pipe line extended. Physical progress 77%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
24 Dec 2021 | 3854 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
20 Dec 2021 | 3854 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
16 Dec 2021 | 3830 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km laying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
12 Dec 2021 | 3828 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE |