Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Jun 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
18 Jun 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
10 Jun 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
01 Jun 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
22 May 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
17 May 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
08 May 2024 | 230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
25 Apr 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
18 Apr 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE | |
06 Apr 2024 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. | Perlassery Sn 2 AE |