Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
18 Jun 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
10 Jun 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
01 Jun 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
22 May 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
17 May 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
08 May 2024 230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
25 Apr 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
18 Apr 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE
06 Apr 2024 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill submitted-Remaining work separately arranged. Perlassery Sn 2 AE