Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Apr 2022 | 4228 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
31 Mar 2022 | 4228 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
27 Mar 2022 | 4224Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
22 Mar 2022 | 4223Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
17 Mar 2022 | 4223Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
14 Mar 2022 | 4223Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
10 Mar 2022 | 4219Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
06 Mar 2022 | 4217 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
02 Mar 2022 | 4171 Nos FHTCS provided. 42 km pipe line extended. Physical progress 82%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
26 Feb 2022 | 4102 Nos FHTCS provided. 42 km pipe line extended. Physical progress 82%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted | Perlassery Sn 2 AE |