Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Apr 2022 4228 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted Perlassery Sn 2 AE
31 Mar 2022 4228 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted Perlassery Sn 2 AE
27 Mar 2022 4224Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted Perlassery Sn 2 AE
22 Mar 2022 4223Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted Perlassery Sn 2 AE
17 Mar 2022 4223Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted Perlassery Sn 2 AE
14 Mar 2022 4223Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted Perlassery Sn 2 AE
10 Mar 2022 4219Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted Perlassery Sn 2 AE
06 Mar 2022 4217 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted Perlassery Sn 2 AE
02 Mar 2022 4171 Nos FHTCS provided. 42 km pipe line extended. Physical progress 82%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted Perlassery Sn 2 AE
26 Feb 2022 4102 Nos FHTCS provided. 42 km pipe line extended. Physical progress 82%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted Perlassery Sn 2 AE