Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 May 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
14 May 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
06 May 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
04 May 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
30 Apr 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
26 Apr 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
22 Apr 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
18 Apr 2022 | 4228 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
15 Apr 2022 | 4228 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
10 Apr 2022 | 4228 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE |