Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Feb 2022 | 4040 Nos FHTCS provided. 42 km pipe line extended. Physical progress 80%. Pipe supply, 38km laying and 4006 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
18 Feb 2022 | 4017 Nos FHTCS provided. 42 km pipe line extended. Physical progress 80%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
14 Feb 2022 | 3987 Nos FHTCS provided. 42 km pipe line extended. Physical progress 79%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
10 Feb 2022 | 3969 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
07 Feb 2022 | 3950 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
03 Feb 2022 | 3938 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
01 Feb 2022 | 3938 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
28 Jan 2022 | 3938 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
24 Jan 2022 | 3938 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
21 Jan 2022 | 3938 Nos FHTCS provided. 42 km pipe line extended. Physical progress 78%. Pipe supply, 38km laying and 3900 nos FHTCS bill submitted | Perlassery Sn 2 AE |