Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Sep 2021 | 3163 Nos FHTCS provided. 40 km pipe line extended. Physical progress 63%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
02 Sep 2021 | 2904 Nos FHTCS provided. 40 km pipe line extended. Physical progress 58%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
28 Aug 2021 | 2875 Nos FHTCS provided. 40 km pipe line extended. Physical progress 57%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
23 Aug 2021 | 2848 Nos FHTCS provided. 40 km pipe line extended. Physical progress 57%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
17 Aug 2021 | 2834 nos FHTCS provided. 40 km pipe line extended. Physical progress 56%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. Part bill under preparation. | Perlassery Sn 2 AE | |
09 Aug 2021 | 2781 nos FHTCS provided. 38 km pipe line extended. Physical progress 55%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted.part bill under preparation. | Perlassery Sn 2 AE | |
05 Aug 2021 | 2717 nos FHTCS provided. 38 km pipe line extended. Physical progress 54%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted.part bill under preparation. | Perlassery Sn 2 AE | |
01 Aug 2021 | 2666 nos FHTCS provided. 38 km pipe line extended. Physical progress 53%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted.part bill under preparation. | Perlassery Sn 2 AE | |
27 Jul 2021 | 2632 nos FHTCS provided. 38 km pipe line extended. Physical progress 52%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted.part bill under preparation. | Perlassery Sn 2 AE | |
27 Jul 2021 | 2632 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted.part bill under preparation. | Perlassery Sn 2 AE |