Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Sep 2021 3163 Nos FHTCS provided. 40 km pipe line extended. Physical progress 63%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. Perlassery Sn 2 AE
02 Sep 2021 2904 Nos FHTCS provided. 40 km pipe line extended. Physical progress 58%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. Perlassery Sn 2 AE
28 Aug 2021 2875 Nos FHTCS provided. 40 km pipe line extended. Physical progress 57%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. Perlassery Sn 2 AE
23 Aug 2021 2848 Nos FHTCS provided. 40 km pipe line extended. Physical progress 57%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. Perlassery Sn 2 AE
17 Aug 2021 2834 nos FHTCS provided. 40 km pipe line extended. Physical progress 56%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. Part bill under preparation. Perlassery Sn 2 AE
09 Aug 2021 2781 nos FHTCS provided. 38 km pipe line extended. Physical progress 55%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted.part bill under preparation. Perlassery Sn 2 AE
05 Aug 2021 2717 nos FHTCS provided. 38 km pipe line extended. Physical progress 54%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted.part bill under preparation. Perlassery Sn 2 AE
01 Aug 2021 2666 nos FHTCS provided. 38 km pipe line extended. Physical progress 53%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted.part bill under preparation. Perlassery Sn 2 AE
27 Jul 2021 2632 nos FHTCS provided. 38 km pipe line extended. Physical progress 52%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted.part bill under preparation. Perlassery Sn 2 AE
27 Jul 2021 2632 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted.part bill under preparation. Perlassery Sn 2 AE