Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Oct 2021 | 3614 Nos FHTCS provided. 42 km pipe line extended. Physical progress 72%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
27 Oct 2021 | 3610 Nos FHTCS provided. 42 km pipe line extended. Physical progress 72%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
23 Oct 2021 | 3610 Nos FHTCS provided. 42 km pipe line extended. Physical progress 72%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
18 Oct 2021 | 3592 Nos FHTCS provided. 42 km pipe line extended. Physical progress 71%. Pipe supply, 38km lying and 3414 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
12 Oct 2021 | 3571 Nos FHTCS provided. 40 km pipe line extended. Physical progress 71%. Pipe supply, 38km lying and 3414 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
06 Oct 2021 | 3533 Nos FHTCS provided. 40 km pipe line extended. Physical progress 70%. Pipe supply, 38km lying and 2827 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
30 Sep 2021 | 3492 Nos FHTCS provided. 40 km pipe line extended. Physical progress 69%. Pipe supply, 38km lying and 2827 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
25 Sep 2021 | 3425 Nos FHTCS provided. 40 km pipe line extended. Physical progress 68%. Pipe supply, 38km lying and 2827 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
20 Sep 2021 | 3333 Nos FHTCS provided. 40 km pipe line extended. Physical progress 66%. Pipe supply, 38km lying and 2827 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
14 Sep 2021 | 3243 Nos FHTCS provided. 40 km pipe line extended. Physical progress 65%. Pipe supply, 27km lying and 2568 nos FHTCS bill submitted. | Perlassery Sn 2 AE |