Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Dec 2021 3828 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3812 nos FHTCS bill submitted. Perlassery Sn 2 AE
04 Dec 2021 3827 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3812 nos FHTCS bill submitted. Perlassery Sn 2 AE
01 Dec 2021 3827 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. Perlassery Sn 2 AE
28 Nov 2021 3822 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. Perlassery Sn 2 AE
24 Nov 2021 3796 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. Perlassery Sn 2 AE
22 Nov 2021 3771 Nos FHTCS provided. 42 km pipe line extended. Physical progress 74%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. Perlassery Sn 2 AE
16 Nov 2021 3716 Nos FHTCS provided. 42 km pipe line extended. Physical progress 74%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. Perlassery Sn 2 AE
12 Nov 2021 3710 Nos FHTCS provided. 42 km pipe line extended. Physical progress 74%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. Perlassery Sn 2 AE
08 Nov 2021 3690 Nos FHTCS provided. 42 km pipe line extended. Physical progress 73%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. Perlassery Sn 2 AE
03 Nov 2021 3651 Nos FHTCS provided. 42 km pipe line extended. Physical progress 73%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. Perlassery Sn 2 AE