Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Dec 2021 | 3828 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
04 Dec 2021 | 3827 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3812 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
01 Dec 2021 | 3827 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
28 Nov 2021 | 3822 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
24 Nov 2021 | 3796 Nos FHTCS provided. 42 km pipe line extended. Physical progress 76%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
22 Nov 2021 | 3771 Nos FHTCS provided. 42 km pipe line extended. Physical progress 74%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
16 Nov 2021 | 3716 Nos FHTCS provided. 42 km pipe line extended. Physical progress 74%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
12 Nov 2021 | 3710 Nos FHTCS provided. 42 km pipe line extended. Physical progress 74%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
08 Nov 2021 | 3690 Nos FHTCS provided. 42 km pipe line extended. Physical progress 73%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE | |
03 Nov 2021 | 3651 Nos FHTCS provided. 42 km pipe line extended. Physical progress 73%. Pipe supply, 38km lying and 3562 nos FHTCS bill submitted. | Perlassery Sn 2 AE |