Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Jul 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill under preparation | Perlassery Sn 2 AE | |
04 Jul 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill under preparation | Perlassery Sn 2 AE | |
30 Jun 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill under preparation | Perlassery Sn 2 AE | |
26 Jun 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted. Remaining bill under preparation | Perlassery Sn 2 AE | |
21 Jun 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
12 Jun 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
09 Jun 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
04 Jun 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
30 May 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE | |
25 May 2022 | 4230 Nos FHTCS provided. 42 km pipe line extended. Physical progress 84%. Pipe supply, 38km laying and 4204nos FHTCS bill submitted | Perlassery Sn 2 AE |