Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Jul 2021 | 2576 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted.part bill under preparation. | Perlassery Sn 2 AE | |
19 Jul 2021 | 2576 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted.part bill under preparation. | Perlassery Sn 2 AE | |
14 Jul 2021 | 2576 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
09 Jul 2021 | 2576 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
05 Jul 2021 | 2517 nos FHTCS provided. 38 km pipe line extended. Physical progress 50%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
02 Jul 2021 | 2457 nos FHTCS provided. 38 km pipe line extended. Physical progress 49%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
30 Jun 2021 | 2398 nos FHTCS provided. 38 km pipe line extended. Physical progress 47%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
01 Jun 2021 | 2118 nos FHTCS provided. 35 km pipe line extended. Physical progress 45%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
21 Apr 2021 | 1969 nos FHTCS provided. 30 km pipe line extended. Physical progress 40%. Pipe supply, 16.5km lying and 1711 nos FHTCS bill submitted | Perlassery Sn 2 AE | |
05 Apr 2021 | 1792 nos FHTCS provided. 30 km pipe line extended. Physical progress 40%. Pipe supply, 16.5km laying and 1711 nos FHTCS bill submitted | Perlassery Sn 2 AE |