Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Jul 2021 2576 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted.part bill under preparation. Perlassery Sn 2 AE
19 Jul 2021 2576 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted.part bill under preparation. Perlassery Sn 2 AE
14 Jul 2021 2576 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted Perlassery Sn 2 AE
09 Jul 2021 2576 nos FHTCS provided. 38 km pipe line extended. Physical progress 51%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted Perlassery Sn 2 AE
05 Jul 2021 2517 nos FHTCS provided. 38 km pipe line extended. Physical progress 50%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted Perlassery Sn 2 AE
02 Jul 2021 2457 nos FHTCS provided. 38 km pipe line extended. Physical progress 49%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted Perlassery Sn 2 AE
30 Jun 2021 2398 nos FHTCS provided. 38 km pipe line extended. Physical progress 47%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted Perlassery Sn 2 AE
01 Jun 2021 2118 nos FHTCS provided. 35 km pipe line extended. Physical progress 45%. Pipe supply, 27km lying and 2109 nos FHTCS bill submitted Perlassery Sn 2 AE
21 Apr 2021 1969 nos FHTCS provided. 30 km pipe line extended. Physical progress 40%. Pipe supply, 16.5km lying and 1711 nos FHTCS bill submitted Perlassery Sn 2 AE
05 Apr 2021 1792 nos FHTCS provided. 30 km pipe line extended. Physical progress 40%. Pipe supply, 16.5km laying and 1711 nos FHTCS bill submitted Perlassery Sn 2 AE