Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Sep 2023 14.47% htc connections and 55.65% pipe laying completed (321+0/2218 HTC connections completed, 39379M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Vadanappilly AE
01 Sep 2023 14.47% htc connections and 55.01% pipe laying completed (321+0/2218 HTC connections completed, 38931M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Vadanappilly AE
24 Aug 2023 14.47% htc connections and 55.01% pipe laying completed (312+9/2218 HTC connections completed, 38931M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work and pipe laying work in progress. Vadanappilly AE
22 Aug 2023 14.06% htc connections and 55.01% pipe laying completed (312+0/2218 HTC connections completed, 38931M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work and pipe laying work in progress. Vadanappilly AE
21 Aug 2023 14.06% htc connections and 55.01% pipe laying completed (312+0/2218 HTC connections completed, 38931M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work and pipe laying work in progress. Vadanappilly AE
19 Aug 2023 14.06% htc connections and 55.01% pipe laying completed (312+0/2218 HTC connections completed, 38931M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work and pipe laying work in progress. Vadanappilly AE
18 Aug 2023 14.06% htc connections and 54.80% pipe laying completed (235+77/2218 HTC connections completed, 38781M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work and pipe laying work in progress Vadanappilly AE
17 Aug 2023 10.6% htc connections and 54.73% pipe laying completed (175+60/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work in progress Vadanappilly AE
16 Aug 2023 10.6% htc connections and 54.73% pipe laying completed (175+60/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work in progress Vadanappilly AE
14 Aug 2023 10.6% htc connections and 54.73% pipe laying completed (175+60/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work in progress Vadanappilly AE