Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Oct 2023 |
17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Due to heavy rain, down pour & land sliding the work has to be stopped at 12.00pm. Yesterday also, the work was stopped by completing 4 length DI pipe due to the protest from labours. |
Vadanappilly AE |
|
29 Sep 2023 |
17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Due to heavy rain, down pour & land sliding the work has to be stopped at 12.00pm. Yesterday also, the work was stopped by completing 4 length DI pipe due to the protest from labours. |
Vadanappilly AE |
|
27 Sep 2023 |
17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. |
Vadanappilly AE |
|
26 Sep 2023 |
17.177% htc connections and 57.25% pipe laying completed (372+15/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. |
Vadanappilly AE |
|
25 Sep 2023 |
17.177% htc connections and 57.25% pipe laying completed (372+15/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. |
Vadanappilly AE |
|
23 Sep 2023 |
16.77% htc connections and 57.25% pipe laying completed (366+6/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. |
Vadanappilly AE |
|
21 Sep 2023 |
16.50% htc connections and 57.25% pipe laying completed (351+15/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. |
Vadanappilly AE |
|
20 Sep 2023 |
15.825% htc connections and 57.25% pipe laying completed (325+26/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Geo tracking of the already laid lines in progress. |
Vadanappilly AE |
|
19 Sep 2023 |
14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Geo tracking of the already laid lines in progress. |
Vadanappilly AE |
|
18 Sep 2023 |
14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress, Geo tracking of the already laid lines in progress. |
Vadanappilly AE |
|