Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Due to heavy rain, down pour & land sliding the work has to be stopped at 12.00pm. Yesterday also, the work was stopped by completing 4 length DI pipe due to the protest from labours. Vadanappilly AE
29 Sep 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Due to heavy rain, down pour & land sliding the work has to be stopped at 12.00pm. Yesterday also, the work was stopped by completing 4 length DI pipe due to the protest from labours. Vadanappilly AE
27 Sep 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. Vadanappilly AE
26 Sep 2023 17.177% htc connections and 57.25% pipe laying completed (372+15/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. Vadanappilly AE
25 Sep 2023 17.177% htc connections and 57.25% pipe laying completed (372+15/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. Vadanappilly AE
23 Sep 2023 16.77% htc connections and 57.25% pipe laying completed (366+6/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. Vadanappilly AE
21 Sep 2023 16.50% htc connections and 57.25% pipe laying completed (351+15/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. Vadanappilly AE
20 Sep 2023 15.825% htc connections and 57.25% pipe laying completed (325+26/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Geo tracking of the already laid lines in progress. Vadanappilly AE
19 Sep 2023 14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Geo tracking of the already laid lines in progress. Vadanappilly AE
18 Sep 2023 14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress, Geo tracking of the already laid lines in progress. Vadanappilly AE