Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Jul 2023 4.82% htc connections and 54.73% pipe laying completed (107+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Due to unexpected heavy rain even though pipe line work was completed roads were not handed over to panchayath for restoration. Now due to rain roads were damaged and restoration work has been arranged through JJM contractor for spreading GSB materials wherever required. Vadanappilly AE
11 Jul 2023 4.82% htc connections and 54.73% pipe laying completed (107+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Due to unexpected heavy rain even though pipe line work was completed roads were not handed over to panchayath for restoration. Now due to rain roads were damaged and restoration work has been arranged through JJM contractor for spreading GSB materials wherever required. Vadanappilly AE
10 Jul 2023 4.82% htc connections and 54.73% pipe laying completed (107+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Due to unexpected heavy rain even though pipe line work was completed roads were not handed over to panchayath for restoration. Now due to rain roads were damaged and restoration work has been arranged through JJM contractor for spreading GSB materials wherever required. Vadanappilly AE
07 Jul 2023 4.82% htc connections and 54.73% pipe laying completed (107+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Due to unexpected heavy rain even though pipe line work was completed roads were not handed over to panchayath for restoration. Now due to rain roads were damaged and restoration work has been arranged through JJM contractor for spreading GSB materials wherever required. Vadanappilly AE
06 Jul 2023 4.82% htc connections and 54.73% pipe laying completed (107+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Due to unexpected heavy rain even though pipe line work was completed roads were not handed over to panchayath for restoration. Now due to rain roads were damaged and restoration work has been arranged through JJM contractor for spreading GSB materials wherever required. Vadanappilly AE
05 Jul 2023 4.82% htc connections and 54.73% pipe laying completed (107+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Vadanappilly AE
04 Jul 2023 4.82% htc connections and 54.73% pipe laying completed (107+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Vadanappilly AE
03 Jul 2023 4.82% htc connections and 54.73% pipe laying completed (95+12/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Vadanappilly AE
03 Jul 2023 4.33% htc connections and 54.73% pipe laying completed (95+1/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Vadanappilly AE
03 Jul 2023 4.33% htc connections and 54.73% pipe laying completed (95+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. Vadanappilly AE