JJM-WSS TO NATTIKA FIRKA Phase II - Thalikulam Panchayath
Project |
JJM-WSS TO NATTIKA FIRKA Phase II - Thalikulam Panchayath |
Project Code |
TCRJJM032211746 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-WSS TO NATTIKA FIRKA Phase II - Thalikulam Panchayath |
Status |
On-going |
District |
Thrissur |
Executing Office |
Vadanappalli Sn |
AS Amount (Rs) |
252162000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
251990000 |
TS Number |
TS/2021-2022/2021/38035 |
Total Bill Submitted (Rs) |
84986702 |
Total Bill Paid (Rs) |
84986702 |
Population Benefitted |
30761 |
Capacity in MLD |
26.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Thalikulam Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jala Jeevan Mission 2021-22 - Augmentation - WSS to Nattika Firka - PHASE II Providing Distribution work, FHTC and existing Tank strengthening to Thalikulam Panchayath |
Vadanappalli Sn |
|
2 |
Jal Jeevan Mission (JJM) - CWSS to Nattika Firka- Thalikulam Panchayath-Additional Work-Shifting house connection-Shifting house connection-Pipeline Work |
Vadanappalli Sn |
|
3 |
JJM-2021-2022-Augmentation of CWSS to N/F phase-II-Providing distribution network and FHTCs to Thalikulam Grama Panchayath-PWD Road restoration-Thalikulam -Nambikadavu road,West Tippu Sulthan road (Snehatheeram beach to Chilanka),West Tippu Sulthan road (Puthiyangadi to Nambikadavu),East Tippu Sulthan road(Kalanji to CSM School)-General Civil work |
Vadanappalli Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
22.18% HTC connections and 86.92% pipe laying completed (492+0/2218 HTC connections completed (61511m pipe laying completed out of 70765m). House connection works in progress |
Vadanappilly AE |
|
12 Jun 2024 |
22.18% HTC connections and 86.92% pipe laying completed (492+0/2218 HTC connections completed (61511m pipe laying completed out of 70765m). House connection works in progress |
Vadanappilly AE |
|
18 Apr 2024 |
22.18% HTC connections and 86.92% pipe laying completed (492+0/2218 HTC connections completed (61511m pipe laying completed out of 70765m). House connection works in progress. |
Vadanappilly AE |
|
08 Apr 2024 |
22.18% HTC connections and 86.92% pipe laying completed (492+0/2218 HTC connections completed (61511m pipe laying completed out of 70765m). House connection works in progress. |
Vadanappilly AE |
|
19 Mar 2024 |
22.18% HTC connections and 86.92% pipe laying completed (492+0/2218 HTC connections completed (61511m pipe laying completed out of 70765m). House connection works in progress. |
Vadanappilly AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/03/2022 |
Scheduled date of Completion of the Project |
20 Jun 2023 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
25 Mar 2022 |