Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Oct 2023 | 17.62% htc connections and 61.989% pipe laying completed (391+0/2218 HTC connections completed, 43867M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
25 Oct 2023 | 17.62% htc connections and 61.472% pipe laying completed (391+0/2218 HTC connections completed, 43501M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
24 Oct 2023 | 17.62% htc connections and 60.853% pipe laying completed (391+0/2218 HTC connections completed, 43063M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
23 Oct 2023 | 17.62% htc connections and 60.438% pipe laying completed (391+0/2218 HTC connections completed, 42769M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
22 Oct 2023 | 17.62% htc connections and 60.098% pipe laying completed (391+0/2218 HTC connections completed, 42529M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
21 Oct 2023 | 17.62% htc connections and 59.59% pipe laying completed (391+0/2218 HTC connections completed, 42169M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
20 Oct 2023 | 17.62% htc connections and 59.025% pipe laying completed (391+0/2218 HTC connections completed, 41769M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
19 Oct 2023 | 17.62% htc connections and 58.812% pipe laying completed (391+0/2218 HTC connections completed, 41619M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
18 Oct 2023 | 17.62% htc connections and 58.247% pipe laying completed (391+0/2218 HTC connections completed, 41219M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
18 Oct 2023 | 17.62% htc connections and 57.79% pipe laying completed (391+0/2218 HTC connections completed, 40899M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE |