Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Oct 2023 17.62% htc connections and 61.989% pipe laying completed (391+0/2218 HTC connections completed, 43867M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
25 Oct 2023 17.62% htc connections and 61.472% pipe laying completed (391+0/2218 HTC connections completed, 43501M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
24 Oct 2023 17.62% htc connections and 60.853% pipe laying completed (391+0/2218 HTC connections completed, 43063M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
23 Oct 2023 17.62% htc connections and 60.438% pipe laying completed (391+0/2218 HTC connections completed, 42769M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
22 Oct 2023 17.62% htc connections and 60.098% pipe laying completed (391+0/2218 HTC connections completed, 42529M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
21 Oct 2023 17.62% htc connections and 59.59% pipe laying completed (391+0/2218 HTC connections completed, 42169M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
20 Oct 2023 17.62% htc connections and 59.025% pipe laying completed (391+0/2218 HTC connections completed, 41769M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
19 Oct 2023 17.62% htc connections and 58.812% pipe laying completed (391+0/2218 HTC connections completed, 41619M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
18 Oct 2023 17.62% htc connections and 58.247% pipe laying completed (391+0/2218 HTC connections completed, 41219M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
18 Oct 2023 17.62% htc connections and 57.79% pipe laying completed (391+0/2218 HTC connections completed, 40899M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE