Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Aug 2023 7.9% htc connections and 54.73% pipe laying completed (146+29/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work in progress Vadanappilly AE
10 Aug 2023 6.58% htc connections and 54.73% pipe laying completed (135+11/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work in progress Vadanappilly AE
07 Aug 2023 6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Due to water table raise the works is temporarily stopped Vadanappilly AE
05 Aug 2023 6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Due to water table raise the works is temporarily stopped Vadanappilly AE
04 Aug 2023 6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.Due to water table raise the works is temporarily stopped Vadanappilly AE
04 Aug 2023 6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.Due to water table raise the works is temporarily stopped Vadanappilly AE
03 Aug 2023 6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.NH pipe laying works started by Sivalaya constructions Vadanappilly AE
02 Aug 2023 6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.NH pipe laying works started by Sivalaya constructions Vadanappilly AE
01 Aug 2023 6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.NH pipe laying works started by Sivalaya constructions Vadanappilly AE
31 Jul 2023 6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Due to water table raise the works is temporarily stopped. C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress. Vadanappilly AE