Status Date |
Overall Project Status |
Project Officer |
Contact |
11 Aug 2023 |
7.9% htc connections and 54.73% pipe laying completed (146+29/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work in progress |
Vadanappilly AE |
|
10 Aug 2023 |
6.58% htc connections and 54.73% pipe laying completed (135+11/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Connection work in progress |
Vadanappilly AE |
|
07 Aug 2023 |
6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi 4 Level stair case - concreting completed. Due to water table raise the works is temporarily stopped |
Vadanappilly AE |
|
05 Aug 2023 |
6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi
4 Level stair case - concreting completed. Due to water table raise the works is temporarily stopped |
Vadanappilly AE |
|
04 Aug 2023 |
6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.Due to water table raise the works is temporarily stopped |
Vadanappilly AE |
|
04 Aug 2023 |
6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.Due to water table raise the works is temporarily stopped |
Vadanappilly AE |
|
03 Aug 2023 |
6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.NH pipe laying works started by Sivalaya constructions |
Vadanappilly AE |
|
02 Aug 2023 |
6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.NH pipe laying works started by Sivalaya constructions |
Vadanappilly AE |
|
01 Aug 2023 |
6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress.NH pipe laying works started by Sivalaya constructions |
Vadanappilly AE |
|
31 Jul 2023 |
6.09% htc connections and 54.73% pipe laying completed (135+0/2218 HTC connections completed, 38731M pipe laying completed out of 70765M), Due to water table raise the works is temporarily stopped. C C Third and part bill submitted. Kacherippadi stair case -shuttering work in progress. |
Vadanappilly AE |
|