Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Oct 2023 | 17.62% htc connections and 57.79% pipe laying completed (391+0/2218 HTC connections completed, 40899M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
16 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE | |
12 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE | |
11 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE | |
10 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE | |
09 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE | |
07 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE | |
06 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE | |
05 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE | |
04 Oct 2023 | 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. | Vadanappilly AE |