Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Oct 2023 17.62% htc connections and 57.79% pipe laying completed (391+0/2218 HTC connections completed, 40899M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
16 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE
12 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE
11 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE
10 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE
09 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE
07 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE
06 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE
05 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE
04 Oct 2023 17.62% htc connections and 57.25% pipe laying completed (387+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Vadanappilly AE