Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Jul 2023 | 4.28% htc connections and 54.31% pipe laying completed (95+0/2218 HTC connections completed, 38431M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
30 Jun 2023 | 4.28% htc connections and 54.03% pipe laying completed (95+0/2218 HTC connections completed, 38231M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
29 Jun 2023 | 4.28% htc connections and 54.03% pipe laying completed (95+0/2218 HTC connections completed, 38231M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
27 Jun 2023 | 4.28% htc connections and 53.76% pipe laying completed (95+0/2218 HTC connections completed, 38041M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
26 Jun 2023 | 4.28% htc connections and 53.47% pipe laying completed (95+0/2218 HTC connections completed, 37839M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
24 Jun 2023 | 4.28% htc connections and 53.13% pipe laying completed (95+0/2218 HTC connections completed, 37606M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
23 Jun 2023 | 4.28% htc connections and 52.79% pipe laying completed (95+0/2218 HTC connections completed, 37359M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
22 Jun 2023 | 4.28% htc connections and 52.44% pipe laying completed (95+0/2218 HTC connections completed, 37109M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
21 Jun 2023 | 4.28% htc connections and 52.23% pipe laying completed (95+0/2218 HTC connections completed, 36959M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
20 Jun 2023 | 4.28% htc connections and 52.23% pipe laying completed (95+0/2218 HTC connections completed, 36959M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE |