Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Sep 2023 14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress, Geo tracking of the already laid lines in progress. Vadanappilly AE
16 Sep 2023 14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress, Geo tracking on progress. Vadanappilly AE
14 Sep 2023 14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress, Geo tracking on progress. Vadanappilly AE
13 Sep 2023 14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. Vadanappilly AE
12 Sep 2023 14.65% htc connections and 57.25% pipe laying completed (321+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. Vadanappilly AE
11 Sep 2023 14.47% htc connections and 57.25% pipe laying completed (321+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Vadanappilly AE
08 Sep 2023 14.47% htc connections and 57.14% pipe laying completed (321+0/2218 HTC connections completed, 40437M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Vadanappilly AE
07 Sep 2023 14.47% htc connections and 57.14% pipe laying completed (321+0/2218 HTC connections completed, 40437M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Geo tracking of the already laid lines are work in progress. Vadanappilly AE
05 Sep 2023 14.47% htc connections and 56.73% pipe laying completed (321+0/2218 HTC connections completed, 40147M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Geo tracking of the already laid lines are work in progress. Vadanappilly AE
04 Sep 2023 14.47% htc connections and 56.73% pipe laying completed (321+0/2218 HTC connections completed, 40147M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Vadanappilly AE