Status Date |
Overall Project Status |
Project Officer |
Contact |
16 Sep 2023 |
14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress, Geo tracking of the already laid lines in progress. |
Vadanappilly AE |
|
16 Sep 2023 |
14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress, Geo tracking on progress. |
Vadanappilly AE |
|
14 Sep 2023 |
14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress, Geo tracking on progress. |
Vadanappilly AE |
|
13 Sep 2023 |
14.65% htc connections and 57.25% pipe laying completed (325+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. |
Vadanappilly AE |
|
12 Sep 2023 |
14.65% htc connections and 57.25% pipe laying completed (321+4/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work in progress. |
Vadanappilly AE |
|
11 Sep 2023 |
14.47% htc connections and 57.25% pipe laying completed (321+0/2218 HTC connections completed, 40515M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. |
Vadanappilly AE |
|
08 Sep 2023 |
14.47% htc connections and 57.14% pipe laying completed (321+0/2218 HTC connections completed, 40437M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. |
Vadanappilly AE |
|
07 Sep 2023 |
14.47% htc connections and 57.14% pipe laying completed (321+0/2218 HTC connections completed, 40437M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Geo tracking of the already laid lines are work in progress. |
Vadanappilly AE |
|
05 Sep 2023 |
14.47% htc connections and 56.73% pipe laying completed (321+0/2218 HTC connections completed, 40147M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. Geo tracking of the already laid lines are work in progress. |
Vadanappilly AE |
|
04 Sep 2023 |
14.47% htc connections and 56.73% pipe laying completed (321+0/2218 HTC connections completed, 40147M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - Hand rail work completed. Connection work and pipe laying work in progress. |
Vadanappilly AE |
|