Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Jun 2023 | 4.28% htc connections and 52.23% pipe laying completed (95+0/2218 HTC connections completed, 36959M pipe laying completed out of 70765M), Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
15 Jun 2023 | 4.28% htc connections and 52.06% pipe laying completed (95+0/2218 HTC connections completed, 36842M pipe laying completed out of 70765M),Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
14 Jun 2023 | 4.28% htc connections and 52% pipe laying completed (95+0/2218 HTC connections completed, 36800M pipe laying completed out of 70765M),Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
13 Jun 2023 | 4.28% htc connections and 52% pipe laying completed (95+0/2218 HTC connections completed, 36800M pipe laying completed out of 70765M),Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
12 Jun 2023 | 4.28% htc connections and 52% pipe laying completed (95+0/2218 HTC connections completed, 36800M pipe laying completed out of 70765M),Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
09 Jun 2023 | 4.28% htc connections and 52% pipe laying completed (95+0/2218 HTC connections completed, 36800M pipe laying completed out of 70765M),Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
08 Jun 2023 | 4.28% htc connections and 52% pipe laying completed (95+0/2218 HTC connections completed, 36800M pipe laying completed out of 70765M),Kacherippadi stair case -Step concrete work in progress. | Vadanappilly AE | |
07 Jun 2023 | 4.28% htc connections and 51.97% pipe laying completed (95+0/2218 HTC connections completed, 36776M pipe laying completed out of 70765M),Kacherippadi stair case -Step form work in progress. | Vadanappilly AE | |
06 Jun 2023 | 4.28% htc connections and 51.55% pipe laying completed (95+0/2218 HTC connections completed, 36476M pipe laying completed out of 70765M),Kacherippadi stair case -Step form work in progress. | Vadanappilly AE | |
05 Jun 2023 | 4.28% htc connections and 51.26% pipe laying completed (95+0/2218 HTC connections completed, 36275M pipe laying completed out of 70765M),Kacherippadi stair case -Column work in progress | Vadanappilly AE |