Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Dec 2023 19.70% HTC connections and 72.97% pipe laying completed (437+0/2218 HTC connections completed, 51641m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
07 Dec 2023 19.70% HTC connections and 72.49% pipe laying completed (437+0/2218 HTC connections completed, 51300m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
04 Dec 2023 19.16% HTC connections and 71.92% pipe laying completed (425+0/2218 HTC connections completed, 50895m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
30 Nov 2023 19.16% HTC connections and 71.51% pipe laying completed (425+0/2218 HTC connections completed, 50605m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
27 Nov 2023 19.16% HTC connections and 71.51% pipe laying completed (425+0/2218 HTC connections completed, 50605m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
24 Nov 2023 19.16% HTC connections and 70.32% pipe laying completed (425+0/2218 HTC connections completed, 49923m pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
20 Nov 2023 19.16% HTC connections and 70.32% pipe laying completed (425+0/2218 HTC connections completed, 49763m pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
18 Nov 2023 19.16% HTC connections and 70.32% pipe laying completed (425+0/2218 HTC connections completed, 49763m pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
13 Nov 2023 17.94% HTC connections and 70.31% pipe laying completed (398+0/2218 HTC connections completed, 49759m pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE
27 Oct 2023 17.62% htc connections and 61.989% pipe laying completed (391+0/2218 HTC connections completed, 43867M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. Vadanappilly AE