Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Dec 2023 | 19.70% HTC connections and 72.97% pipe laying completed (437+0/2218 HTC connections completed, 51641m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
07 Dec 2023 | 19.70% HTC connections and 72.49% pipe laying completed (437+0/2218 HTC connections completed, 51300m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
04 Dec 2023 | 19.16% HTC connections and 71.92% pipe laying completed (425+0/2218 HTC connections completed, 50895m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
30 Nov 2023 | 19.16% HTC connections and 71.51% pipe laying completed (425+0/2218 HTC connections completed, 50605m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
27 Nov 2023 | 19.16% HTC connections and 71.51% pipe laying completed (425+0/2218 HTC connections completed, 50605m pipe laying completed out of 70765m), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
24 Nov 2023 | 19.16% HTC connections and 70.32% pipe laying completed (425+0/2218 HTC connections completed, 49923m pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
20 Nov 2023 | 19.16% HTC connections and 70.32% pipe laying completed (425+0/2218 HTC connections completed, 49763m pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
18 Nov 2023 | 19.16% HTC connections and 70.32% pipe laying completed (425+0/2218 HTC connections completed, 49763m pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
13 Nov 2023 | 17.94% HTC connections and 70.31% pipe laying completed (398+0/2218 HTC connections completed, 49759m pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE | |
27 Oct 2023 | 17.62% htc connections and 61.989% pipe laying completed (391+0/2218 HTC connections completed, 43867M pipe laying completed out of 70765M), C C Third and part bill submitted. Kacherippadi stair case - plastering work completed. | Vadanappilly AE |