Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Jan 2021 |
27%of the work in package-1 completed, 5399m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site and 714m of 600 mm DI K9 RWPM laid in a total of 2770m, RCC side wall work in progress for 36.50 LL sump of WTP, filter shell, clarifier,flocculator etc .RCC foundation works of 23 LL OHSR at Safa college compound up to plinth beams completed. In package-2 distribution systom-Supply order given for DI pipes package-3-work order on hold due to technical reason, for confirming the type of transformer |
Malappuram Project Dn AE5 |
|
26 Jan 2021 |
25% of the work in package-1 completed, 5399m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site and 714m of 600 mm DI K9 RWPM laid in a total of 2770m, RCC side wall work in progress for 36.50 LL sump of WTP, filter shell, clarifier,flocculator etc .RCC foundation works of 23 LL OHSR at Safa college compound up to plinth beams completed.
In package-2 distribution systom-Supply order given for DI pipes
package-3-work order on hold due to technical reason, for confirming the type of transformer |
Malappuram Project Dn AE5 |
|
26 Jan 2021 |
25% Completed | 25% of the work in package-1 completed, 5399m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site and 714m of 600 mm DI K9 RWPM laid in a total of 2770m, RCC side wall work in progress for 36.50 LL sump of WTP, filter shell, clarifier,flocculator etc .RCC foundation works of 23 LL OHSR at Safa college compound up to plinth beams completed. For distribution network agreement executed and DI pipes ordered |
Malappuram Project Dn AE5 |
|
21 Nov 2020 |
15% of the work in package-1 completed, 1300 m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site.Excavation completed for 36 LL sump of WTP and concreting will commence next week,Excavation work for filter bed,clarifier,flocculator etc in progress and also for the foundation of 23 LL OHSR at Safa college compound.
Tendering process completed for package-2 (Distribution network-145 KM).Tender sanctioned and work order given and agreement to be executed,
Package-3,electro mechanical works tendered,tender closing date is 2/12/2020 |
Malappuram Project Dn AE5 |
|
15 Nov 2020 |
12 % of the work in package-1 completed, Pipe laying started for 350mm DI K9 CWPM from proposed plant site to propopsed 23 LL OHSR site.Excavation in progress for 36 LL sump,filter bed,et and etc and also for the foundation of 23 LL OHSR at Safa college compound.
Tendering process completed for package-2 (Distribution network).Tender sanctioned and work order given
Package-3,electro mechanical works tendered
|
Malappuram Project Dn AE5 |
|
12 Oct 2020 |
Pipes (600mm DI K9 and 350mm DI K9) arrived for RWPM from existing well to ongoing WTP and CWPM from ongoing WTP to ongoing 23LL OHSR of Edayur GP at Safa college compound respectively.Agreement executed with PWD .Laying work will start in this week itself.TS approval got for Packages 1 &2 from KIIFB.Tendering process of Package-2(distribution network) completed.Hydrullic and structural drawing of components of package-1 under verification |
Malappuram Project Dn AE5 |
|
16 Aug 2020 |
Approval of packages1,2 under process,Hydraullic design,structural drawing of components of package 1 under process.Package 2 tendered |
Malappuram Project Dn AE5 |
|
01 Jul 2020 |
work just started for WTP and OHSR.Site clearence and levelling has done |
Malappuram Project Dn AE5 |
|