Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Nov 2021 In Package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed. Construction of compound wall in progress. At WTP Mechanical works in progress. Handrail fittings started. In Package 2, 21410 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In Package 3, Construction of Transformer Room In progress. (Structural Work Completed) Malappuram Project Dn AE5
18 Oct 2021 In Package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works and construction of compound wall in progress. At WTP Mechanical works in progress. In package 2, 17465 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer Room In progress. (Structural Work Completed) Malappuram Project Dn AE5
25 Sep 2021 In Package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works and construction of compound wall in progress. At WTP Mechanical works in progress.In Package 2, 11440 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer Room In progress. Malappuram Project Dn AE5
24 Sep 2021 In package-1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP RCC structural work of 37.5 LL Sump,Filter house,Flocculator,Clarifier Airator,Flashmixer etc completed. Finishing work and mechanical work ongoing. At Safa OHSR RCC structural works completed, plastering works and construction of compound wall in progress. In package 2, Distribution- 12500 m PVC pipes laid. In package 3, Construction of Transformer Room In progress. Malappuram Project Dn AE5
27 Aug 2021 In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP RCC structural work of 37.5 LL Sump,Filter house,Flocculator,Clarifier etc completed Airator,Flashmixer and Roof slab work and Plastering work of 37.50 LL sump completed. At Safa OHSR RCC structural works completed, plastering works and construction of compound wall in progress. In package 2, Distribution- 4776 m PVC pipes laid. In package 3, Construction of Transformer Room In progress. Malappuram Project Dn AE5
12 Aug 2021 In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP RCC structural work of 37.5 LL Sump,Filter house,Flocculator,Clarifier etc completed Airator,Flashmixer and Roof slab work of Wash water Tank in progress . Plastering work of 37.50 LL sump completed. RCC structural works of Roof slab concrete work completed in Safa OHSR and plastering work started. In package -2 distribution system- a part of PVC pipes( 7 KM) arrived at site and laying work started. In package -3 electro mechanical works- Agreement executed on 14/05/2021 and construction of transformer building started. Malappuram Project Dn AE5
12 Jul 2021 In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP RCC structural work of 37.5 LL Sump,Filter house,Flocculator,Clarifier etc completed Airator,Flashmixer and Roof slab work of Wash water Tank in progress . Plastering work of 37.50 LL sump completed. RCC structural works of Roof slab concrete work completed in Safa OHSR and plastering work started. In package -2 distribution systom- a part of PVC pipes( 7 KM) arrived at site. In package -3 electro mechanical works- Agreement executed on 14/05/2021 Malappuram Project Dn AE5
11 Jul 2021 In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP RCC structural work of 37.5 LL Sump,Filter house,Flocculator,Clarifier etc completed Airator,Flashmixer and Roof slab work of Wash water Tank in progress . Plastering work of 37.50 LL sump completed. RCC structural works of Roof slab concrete work completed in Safa OHSR and plastering work started. In package -2 distribution systom- a part of PVC pipes( 7 KM) arrived at site. In package -3 electro mechanical works- Agreement executed on 14/05/2021 Malappuram Project Dn AE5
01 Jul 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR for Edayur GP at Safa college and 800m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP floor slab and Roof slab of filter house work completed. Roof slab concrete work Completed in Safa OHSR. Airator work started at WTP. Plastering work of sump in progress.In package 2, PVC pipe expected to receive next week.In package 3, Agreement executed on 14/05/2021 Malappuram Project Dn AE5
16 Jun 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR for Edayur GP at Safa college and 800m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP floor slab work of wash water tank in progress. Roof slab concrete work in Completed and Areator work started at Safa OHSR. In package 2, PVC pipe expected to receive next week. In package 3, Agreement executed on 14/05/2021 Malappuram Project Dn AE5