Status Date Overall Project Status Project Officer Contact
13 Apr 2021 In package 1, At safa side wall concreting in progress. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered Malappuram Project Dn AE5
12 Apr 2021 In package 1, At safa side wall concreting in progress. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered Malappuram Project Dn AE5
09 Apr 2021 In package 1, At Safa reinforcement work of first stage of side wall in progress. Roof beam work of 36.50 LL sump in progress. Masonry work of wall of WTP building in progress. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered Malappuram Project Dn AE5
08 Apr 2021 In package 1, At Safa reinforcement work of first stage of side wall in progress. Roof beam work of 36.50 LL sump in progress. Masonry work of wall of WTP building in progress. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered. Malappuram Project Dn AE5
07 Apr 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site at Safa college and 714m of 600 mm DI K9 RWPM laid in a total of 2770m, RCC side wall work in progress for 36.50 LL sump of WTP, filter shell, clarifier , flocculator etc. First floor slab of WTP building completed. Alum lime mixing tank work in progress. Floor beam and floor slab of OHSR at safa completed. Masonry work of wall of WTP Building in progress. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered. Malappuram Project Dn AE5
05 Apr 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site at Safa college and 714m of 600 mm DI K9 RWPM laid in a total of 2770m, RCC side wall work in progress for 36.50 LL sump of WTP, filter shell, clarifier , flocculator etc. First floor slab of WTP building completed. Alum lime mixing tank work in progress. Floor beam and floor slab of OHSR at safa completed. Masonry work of wall of WTP Building in progress. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered. Malappuram Project Dn AE5
03 Apr 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site at Safa college and 714m of 600 mm DI K9 RWPM laid in a total of 2770m, RCC side wall work in progress for 36.50 LL sump of WTP, filter shell, clarifier , flocculator etc. First floor slab of WTP building completed. Alum lime mixing tank work in progress. Floor beam and floor slab of OHSR at safa completed. Masonry work of wall of WTP Building in progress. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered. Malappuram Project Dn AE5
10 Mar 2021 29%of the work in package-1 completed, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site and 714m of 600 mm DI K9 RWPM laid in a total of 2770m, RCC side wall work in progress for 36.50 LL sump of WTP, filter shell, clarifier,flocculator etc .RCC floor beam,floor slab works of 23 LL OHSR at Safa college compound etc are in progress. In package-2 distribution systom-Supply order given for DI pipes.Package-3 Recasted estimate prepared as per deviation and work tenderd Malappuram Project Dn AE5
16 Feb 2021 28%of the work in package-1 completed, 5450m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site and 714m of 600 mm DI K9 RWPM laid in a total of 2770m, RCC side wall work in progress for 36.50 LL sump of WTP, filter shell, clarifier,flocculator etc .RCC floor beam works of 23 LL OHSR at Safa college compound completed. In package-2 distribution systom-Supply order given for DI pipes.Package-3,rRecasted estimate prepared as per deviation Malappuram Project Dn AE5
05 Feb 2021 28% of works in package-l completed Malappuram Project Dn AE5