Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Jan 2022 |
In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress ( Column work started). In package 2, 31140 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer room in progress ( Plastering Work Completed). |
Malappuram Project Dn AE5 |
|
04 Jan 2022 |
In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress ( PCC work completed). In package 2, 31140 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer room in progress ( Plastering Work Completed). |
Malappuram Project Dn AE5 |
|
30 Dec 2021 |
In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work started. In package 2, 29470 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer room in progress ( Plastering Work Completed). |
Malappuram Project Dn AE5 |
|
21 Dec 2021 |
In Package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed. Construction of compound wall in progress. At WTP Mechanical works in progress. Handrail fittings in progress. Painting Work under progress. In Package 2, 27250 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer room in progress ( Plastering Work Completed) |
Malappuram Project Dn AE5 |
|
21 Dec 2021 |
In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed. Construction of compound wall in progress. At WTP Mechanical works in progress. Handrail fittings in progress. Painting Work under progress. In package 2, 26715 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In Package 3, Construction of Transformer room in Progress (Plastering Work Completed). |
Malappuram Project Dn AE5 |
|
16 Dec 2021 |
In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed. Construction of compound wall in progress. At WTP Mechanical works in progress. Handrail fittings in progress. Painting Work under progress. In package 2, 26715 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In Package 3, Construction of Transformer room in Progress (Plastering Work Completed). |
Malappuram Project Dn AE5 |
|
09 Dec 2021 |
In Package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed. Construction of compound wall in progress. At WTP Mechanical works in progress. Handrail fittings in progress. Painting Work under progress. In Package 2, 24415 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer Room In progress. (Plastering Work Completed). |
Malappuram Project Dn AE5 |
|
02 Dec 2021 |
In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed. Construction of compound wall in progress. At WTP Mechanical works in progress. Handrail fittings in progress. White Washing Work in progress.in package 2, 23270 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer room in progress ( Plastering work completed) |
Malappuram Project Dn AE5 |
|
25 Nov 2021 |
In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed. Construction of compound wall in progress. At WTP Mechanical works in progress. Handrail fittings in progress. White Washing Work in progress. In package 2, 22510 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer Room In progress. (Plastering Work Completed). |
Malappuram Project Dn AE5 |
|
19 Nov 2021 |
In Package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed. Construction of compound wall in progress. At WTP Mechanical works in progress. Handrail fittings started. In packge 2, 22070 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In Package 3, Construction of Transformer Room In progress. (Plastering Work Completed). |
Malappuram Project Dn AE5 |
|