10 Jun 2022 In package 1, 92 % - 6800 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work in progress. sub station building work in progress (Plastering and compound wall work in progress). bridge work completed. In package 2, 53 % - 71170 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1939 m, 300 DI 762.5 m, 200 DI 390 m and 250 DI 3180 m laid. In package 3, 15 % - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
30 May 2022 In package 1, 92 % - 6800 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work in progress. sub station building work in progress (Plastering and compound wall work in progress). bridge work in progress. In package 2, 51% - 68550 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1939 m, 300 DI 762.5 m, 200 DI 390 m and 250 DI 3180 m laid. In package 3, 13 % - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
21 May 2022 In package 1, 91 % - 6800 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work in progress. sub station building work in progress (Plastering and compound wall work in progress). In package 2, 50 % - 65900 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1939 m, 300 DI 762.5 m, 200 DI 390 m and 250 DI 3180 m laid. In package 3, 13 % - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
10 May 2022 In package 1, 91 5 - 6800 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work in progress. sub station building work in progress (Plastering and compound wall work in progress). In package 2, 50 % - 63230 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1939 m, 300 DI 762.5 m, 200 DI 390 m and 250 DI 3180 m laid. In package 3, 13 % - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
29 Apr 2022 In package 1, 90 % - 6020 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work in progress. sub station building work in progress (Plastering and compound wall work in progress). In package 2, 47 % - 60030 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1308.5 m, 300 DI 762.5 m, 200 DI 148.5 m and 250 DI 3180 m laid. In package 3, 13 % - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
20 Apr 2022 In package 1, 87 % - 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2400 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work in progress. sub station building work in progress (Concrete work of roof beam and slab completed). In package 2, 43 % - 58500 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1308.5 m, 300 DI 762.5 m, 200 DI 148.5 m and 250 DI 2970 m laid. In package 3, 13 % - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
11 Apr 2022 In package 1, 86%- 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1998.5 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work in progress. sub station building work in progress (Concrete work of roof beam and slab completed).In package 2, 43% - 57650 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1308.5 m, 300 DI 762.5 m, 200 DI 148.5 m and 250 DI 2140 m laid. In package 3, 12% - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
08 Apr 2022 In package 1, 86% - 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1943.5 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work in progress. sub station building work in progress (Concrete work of roof beam and slab completed). In package 2, 43% - 57650 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1308.5 m, 300 DI 762.5 m, 200 DI 148.5 m and 250 DI 2140 m laid. In package 3, 12% - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
01 Apr 2022 In package 1, 85% - 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1817 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. Compound wall work started. sub station building work in progress (steel work of roof beam and slab in progress). In package 2, 42% - 57080 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1308.5 m, 300 DI 762.5 m, 200 DI 148.5 m and 250 DI 1430 m laid. In package 3, 12% - Construction of Transformer Room In progress. (Finishing Work in progress), has arrived transformer. Malappuram Project Dn AE5
22 Mar 2022 In package 1, 84% - 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1767.5 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress (Column work completed). In package 2, 56070 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1308.5 m, 300 DI 762.5 m, 200 DI 148.5 m and 250 DI 260 m laid. In package 3, 11% - Construction of Transformer Room In progress. (Finishing Work in progress). Malappuram Project Dn AE5