02 Jun 2021 n package 1, 5500m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR for Edayur GP at Safa college and 820m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP floor slab work of wash water tank in progress. Roof beam work in final stage at Safa OHSR. In Package 2-distribution network,PVC pipes are expected to arrive next week. Package-3-Electro mechanical work-agreement executed 0n 14/05/2021 Malappuram Project Dn AE5
01 Jun 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR for Edayur GP at Safa college and 800m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP floor slab work of wash water tank in progress. Roof beam work in final stage at Safa OHSR. In Package 2-distribution network,PVC pipes are expected to arrive next week. Package-3-Electro mechanical work-work order given Malappuram Project Dn AE5
26 May 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site at Safa college and 714m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP floor beam work of wash water tank in progress. Side wall work in final stage at Safa OHSR. In package 2, PVC pipe expected to receive next week. In package 3, Work order given on 5/5/2021 Malappuram Project Dn AE5
06 May 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site at Safa college and 714m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP floor beam work of wash water tank in progress. At safa third stage of side wall in safa OHSR completed. In package 2, PVC pipe expected to receive next week. In package 3, Work retendered after obtaining revised TS Malappuram Project Dn AE5
05 May 2021 In package 1, At WTP floor beam work of wash water tank in progress. At safa third stage of side wall in safa OHSR completed. In package 2, PVC pipe expected to receive next week. In package 3, Work retendered after obtaining revised TS Malappuram Project Dn AE5
26 Apr 2021 In package 1, At WTP roof slab work of 36.50 LL sump completed. first floor work of WTP building in progress,At Safa first stage & second stage of side wall in safa OHSR completed. In package 2, Agreement executed. Pipes ordered. Joint Inspection with PWD completed for restoration. In package 3, Work retendered after obtaining revised TS Malappuram Project Dn AE5
26 Apr 2021 In package 1, At WTP roof slab work of 36.50 LL sump completed. first floor work of WTP building in progress,At Safa first stage & second stage of side wall in safa OHSR completed. In package 2, Agreement executed. Pipes ordered. Joint Inspection with PWD completed for restoration. In package 3, Package-3 Work retendered after obtaining revised TS Malappuram Project Dn AE5
21 Apr 2021 Package-1 - RWPM 600mm DI(K9)_laid 850m out of 2770m CWPM 350mm DI(K9)-laid 5860m out of 8400m 26mld WTP-Rcc structural work of filter house up to first floor,Clarifier, Flocculators and 36.50 LL Sump completed 23LLOHSR-Rcc work up to 1m of side wall completed Package-2- Distribution DI and PVC pipes of total length 147 km To be supplied, Inspection with PWD completed Package-3 Work retendered after obtaining revised TS Malappuram Project Dn AE5
19 Apr 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site at Safa college and 714m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP roof slab work of 36.50 LL sump in progress,first floor work of WTP building in progress,At Safa first stage of side wall in safa OHSR completed. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered. Malappuram Project Dn AE5
15 Apr 2021 In package 1, 5480m 350mm DI K9 CWPM laid in a total of of 8400m from ongoing plant site to ongoing 23 LL OHSR site at Safa college and 714m of 600 mm DI K9 RWPM laid in a total of 2770m. At WTP roof slab work of 36.50 LL sump in progress,first floor work of WTP building in progress,At Safa first stage of side wall in safa OHSR completed. In package 2, Joint Inspection with PWD completed. In package 3, Work Tendered. Malappuram Project Dn AE5