Status Date Overall Project Status Project Officer Contact
15 Mar 2022 In package 1, 84%- 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1767.5 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress (Column work completed). In package 2, 42%- 55930 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1308.5 m, 300 DI 762.5 m, and 200 DI 148.5 m laid. In package 3, 11%- Construction of Transformer Room In progress. (Finishing Work in progress). Malappuram Project Dn AE5
07 Mar 2022 In package 1, 84%- 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1756.5 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress (Column work in progress). In package 2, 42%- 55930 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1308.5 m, 300 DI 597.5 m, and 200 DI 148.5 m laid. In package 3, 11%- Construction of Transformer Room In progress. (Finishing Work in progress). Malappuram Project Dn AE5
28 Feb 2022 In package 1, 83%- 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1668.5 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress (Concrete work completed). In package 2, 41%- 55660 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1215 m, 300 DI 357.5 m, and 200 DI 148.5 m laid. In package 3, 10% - Construction of Transformer Room In progress. (Finishing Work in progress). Malappuram Project Dn AE5
19 Feb 2022 In package 1, 83 % 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1575 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress (Centering work in progress). In package 2, 41 % - 55360 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 890 m, 300 DI 357.5 m, and 200 DI 148.5 m laid. In package 3, 10% - Construction of Transformer Room In progress. (Finishing Work in progress). Malappuram Project Dn AE5
12 Feb 2022 In package 1, 82%- 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1443 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress ( Beam concrete work completed). In package 2, 40%- 54850 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 616 m, 300 DI 357.5 m, and 200 DI 148.5 m laid. In package 3, 10% - Construction of Transformer Room In progress. (Finishing Work in progress). Malappuram Project Dn AE5
05 Feb 2022 In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1210 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress ( Column concrete work completed). In package 2 , 54600 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer Room In progress. (Finishing Work in progress). Malappuram Project Dn AE5
30 Jan 2022 In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress ( Steel work of columns in progress). In package 2,53150 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer room in progress. (Finishing work in progress). Malappuram Project Dn AE5
25 Jan 2022 In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress ( Plinth beam concrete work completed ).In package 2, 52270 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer Room In progress. (Finishing Work in progress) Malappuram Project Dn AE5
18 Jan 2022 In Package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress ( Footing work completed and steel work of plinth beam in progress ). In Package 2, 52120 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In Package 3, Construction of Transformer Room In progress. (Plastering Work Completed) Malappuram Project Dn AE5
11 Jan 2022 In package 1, 5480m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 1000m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR RCC structural works completed, plastering works completed and Construction of compound wall completed. At WTP Mechanical works in progress. Handrail fittings completed. Painting Work under progress. sub station building work in progress ( Footing work partially completed ). In package 2, 32580 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. In package 3, Construction of Transformer room in progress ( Plastering Work Completed). Malappuram Project Dn AE5