Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Feb 2023 In package 1, 96%- 7874 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. In package 2, 81%- 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 1950 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid. Anchor block and valve chamber work in progress. PWD BM Work one side completed. In package 3, 92%- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). Malappuram Project Dn AE3
15 Feb 2023 In package 1, 96 % - 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. In package 2, 80 % - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 561 m, 350 DI 1950 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid. Anchor block and valve chamber work in progress. PWD BM Work one side completed. In package 3, 91 % - Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). Malappuram Project Dn AE3
31 Jan 2023 In package 1, 96 % - 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. In package 2, 77 % - 90005 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 352 m, 350 DI 1939 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid. Road restoration GSB wet mix filling work completed in PWD roads. Anchor block and valve chamber work in progress. PWD BM Work in progress. In package 3, 91 % -Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). Amount for powerline extension to KESB is deposited and the material supply order is issued by KSEB for powerline extension work. Malappuram Project Dn AE3
25 Jan 2023 In package 1, 96 % - 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. In package 2, 77 % - 90005 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 352 m, 350 DI 1939 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid. Road restoration GSB wet mix filling work completed in PWD roads. Anchor block and valve chamber work in progress. PWD BM Work in progress. In package 3, 91 % -Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). Malappuram Project Dn AE3
23 Jan 2023 In package 1, 96 %- 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from WTP site to 23 LL OHSR for Edayur GP at Safa campus and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. 350 DI pipeline fabrication work in inter connection gap under progress. 95% work at WTP ste completed. In package 2, 77 %- 90005 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 324.5m, 350 DI 1939 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid. Road restoration GSB wet mix filling work completed in PWD roads. Anchor block and valve chamber work in progress. PWD BM Work in progress. In package 3, 90%- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). Malappuram Project Dn AE3
05 Jan 2023 In package 1, 96 %- 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. In package 2, 72 %- 90005 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 11 m, 350 DI 1939 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid.Road restoration GSB wet mix filling work completed in PWD roads. Anchor block and valve chamber work in progress. PWD BM Work in progress. In package 3, 90%- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). Malappuram Project Dn AE3
20 Dec 2022 In package 1, 96%- 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. In package 2, 70%- 90005 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1939 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid.Road restoration GSB wet mix filling work under process in PWD roads. Anchor block and valve chamber work in progress. PWD BM Work in progress. In package 3, 89%- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). Malappuram Project Dn AE3
12 Dec 2022 In package 1, 96%* 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 69 %- 90005 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1939 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid.Road restoration GSB wet mix filling work under process in PWD roads. Anchor block and valve chamber work in progress. PWD BM Work in progress. Package 3, 87 %- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed) Malappuram Project Dn AE3
17 Nov 2022 In package 1, 96 % - 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work in progress. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. In package 2, 67%- 90005 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1939 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid.Road restoration GSB wet mix filling work under process in PWD roads. Anchor block and valve chamber work in progress. In package 3, 68%- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed.) Malappuram Project Dn AE3
28 Oct 2022 In package 1, 96 % - 7050 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work in progress. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering started. In package 2, 67 % - 90005 M PVC pipes laid. 61.4 KM PVC pipes of various sizes received and laying work ongoing. 350 DI 1939 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid.Road restoration GSB wet mix filling work under process in PWD roads. Anchor block work in progress. In package 3, 60 % - Construction of Transformer Room finishing work in progress. Pump set errection started. Malappuram Project Dn AE3