Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Budget 2017-18-KIIFB-TRAN 10-WRD025-05:WSS to Edayur Panchayath of Malappuram District

Project Budget 2017-18-KIIFB-TRAN 10-WRD025-05:WSS to Edayur Panchayath of Malappuram District
Project Code MLPKIIFB1118553
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description This project contain 3 packages Package-1 : Renovation of existing pump house,Gantry girder,Substation building,600mm RWPM,26 MLD WTP,25.20 LL GLSR, 23 LL OHSR 350mm CWPM,67 HP CF CW pump set Package-2 - Distribution system DI and PVC pipes-115KM Package 3- Electromechanical Works - 270 HP VT RW pumpset, Power line and transformers
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 721700000
AS Number GO(Rt)No34/2018
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 489138925
Total Bill Paid (Rs) 489138925
Population Benefitted 120400
Capacity in MLD 26.00
Actual Project Completion Date 31 Dec 2022
Coverage Edayur Panchayath, Irimbiliyam Pt, Valancheri Municipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Budget 2017-18-KIIFB-TRAN 10-WRD025-05:WSS to Edayur Panchayath of Malappuram District-Package-1(Renovation of existing pump house,Gantry girder,Substation building,600mm RWPM,26 MLD WTP,25.20 LL GLSR,350mm CWPM,67 HP pump set,Restoration of road cutting) Project Division Malappuram
2 KIIFB-Budget-2017-2018- Project -TRAN 10-WAD 025-05-WSS to Edayur Panchayath including service level improvement of existing WSS to Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District(Package-II:Distribution System. Project Division Malappuram
3 KIIFB-Budget-2017-2018- Project-TRAN 10-WRD 025-05:WSS TO Edayur Panchayath including service level improvement of existing WSS TO Irimbiliyam Panchayath and Valanchery Municipality in Malappuram District.(PACKAGE III:Electro Mechanic Works- Transformers IN RWPH and WTP sites &Pumpsets in RWPH) Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Nov 2023 In package 1, 97% - RWPM, CWPM, 26 MLD WTP, 23 LL OHSR are Completed. Interconnection of Raw water pumping main to the existing well and commissioning of the scheme is to be done after getting the KSEB power connection. in package 2, 91% - 13.245 km DI, 108.796 km PVC and 989.8 m GI Pipes are Laid. In package 3, 94% - Construction of Transformer Room Completed. Pump set erection progress. Transformer Supply and erection Completed. Malappuram Project Dn AE3
12 Sep 2023 In Package 1, 97% - 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 91% - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 2500 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid. Anchor block and valve chamber work in progress. Package 3, 94% - Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). Malappuram Project Dn AE3
01 Aug 2023 In package 1, 97% - 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 91% - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 3151 m, 300 DI 1614 m, 200 DI 807.5 m and 250 DI 3273.5 m laid. Anchor block and valve chamber work in progress. Package 3, 94% - Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). For power connection, line extension (Arial Bunched Cable(ABC)) and post errection works of KSEB Under progress. Malappuram Project Dn AE3
18 Jul 2023 In Package 1, 97% - 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 91% - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 3151 m, 300 DI 1614 m, 200 DI 807.5 m and 250 DI 3273.5 m laid. Anchor block and valve chamber work in progress. Package 3, 94% - Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). For power connection, line extension (Arial Bunched Cable(ABC)) and post errection works of KSEB Under progress. Malappuram Project Dn AE3
30 Jun 2023 In package 1, 96% - 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 91% - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 3151 m, 300 DI 1614 m, 200 DI 807.5 m and 250 DI 3273.5 m laid. Anchor block and valve chamber work in progress. Package 3, 94%- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). For power connection, line extension (Arial Bunched Cable(ABC)) and post errection works of KSEB Under progress. Malappuram Project Dn AE3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/03/2020
Scheduled date of Completion of the Project 31 Dec 2023
Expected date of Completion 31/12/2023

Processing Dates

AS Date 19 Nov 2018
TS Date 02 Feb 2019

Other details

Project Officers View