Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Nov 2023 |
In package 1, 97% - RWPM, CWPM, 26 MLD WTP, 23 LL OHSR are Completed. Interconnection of Raw water pumping main to the existing well and commissioning of the scheme is to be done after getting the KSEB power connection. in package 2, 91% - 13.245 km DI, 108.796 km PVC and 989.8 m GI Pipes are Laid. In package 3, 94% - Construction of Transformer Room Completed. Pump set erection progress. Transformer Supply and erection Completed.
|
Malappuram Project Dn AE3 |
|
12 Sep 2023 |
In Package 1, 97% - 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 91% - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 2500 m, 300 DI 1614 m, 200 DI 440 m and 250 DI 3180 m laid. Anchor block and valve chamber work in progress. Package 3, 94% - Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). |
Malappuram Project Dn AE3 |
|
01 Aug 2023 |
In package 1, 97% - 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 91% - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 3151 m, 300 DI 1614 m, 200 DI 807.5 m and 250 DI 3273.5 m laid. Anchor block and valve chamber work in progress. Package 3, 94% - Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). For power connection, line extension (Arial Bunched Cable(ABC)) and post errection works of KSEB Under progress.
|
Malappuram Project Dn AE3 |
|
18 Jul 2023 |
In Package 1, 97% - 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 91% - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 3151 m, 300 DI 1614 m, 200 DI 807.5 m and 250 DI 3273.5 m laid. Anchor block and valve chamber work in progress. Package 3, 94% - Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). For power connection, line extension (Arial Bunched Cable(ABC)) and post errection works of KSEB Under progress.
|
Malappuram Project Dn AE3 |
|
30 Jun 2023 |
In package 1, 96% - 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 91% - 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 3151 m, 300 DI 1614 m, 200 DI 807.5 m and 250 DI 3273.5 m laid. Anchor block and valve chamber work in progress. Package 3, 94%- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). For power connection, line extension (Arial Bunched Cable(ABC)) and post errection works of KSEB Under progress.
|
Malappuram Project Dn AE3 |
|