Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Nov 2020 | Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 24156.50 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu - 23 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded, Estimate preparation in progress. Land Acquisition for construction of substation building already completed. Over all 72 % of work completed. | Kollam Project HD | |
26 Nov 2020 | Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 24085 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at manichithodu - 23 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded, Estimate preparation in progress. Land Acquisition for construction of substation building already completed. Over all 72 % of work completed. | Kollam Project HD | |
17 Nov 2020 | Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 23780.92 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at manichithodu - 20 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded,Estimate preparation in progress. Land Acquisition for construction of substation building already completed.Over all 70 % of work completed. | Kollam Project HD | |
17 Nov 2020 | Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 23780.92 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at manichithodu - 20 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded,Estimate preparation in progress. Land Acquisition for construction of substation building already completed. | Kollam Project HD | |
17 Nov 2020 | Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 23651.52 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at manichithodu - 20 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded,Estimate preparation in progress. Land Acquisition for construction of substation building alredy completed. Over all 70 % of work completed | Kollam Project HD | |
15 Nov 2020 | Construction of 20LL OHSR at TP site and road restoration works completed ,balance works in progress | Kollam Project HD |