Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Nov 2020 Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 24156.50 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu - 23 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded, Estimate preparation in progress. Land Acquisition for construction of substation building already completed. Over all 72 % of work completed. Kollam Project HD
26 Nov 2020 Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 24085 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at manichithodu - 23 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded, Estimate preparation in progress. Land Acquisition for construction of substation building already completed. Over all 72 % of work completed. Kollam Project HD
17 Nov 2020 Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 23780.92 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at manichithodu - 20 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded,Estimate preparation in progress. Land Acquisition for construction of substation building already completed.Over all 70 % of work completed. Kollam Project HD
17 Nov 2020 Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 23780.92 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at manichithodu - 20 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded,Estimate preparation in progress. Land Acquisition for construction of substation building already completed. Kollam Project HD
17 Nov 2020 Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 23651.52 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at manichithodu - 20 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded,Estimate preparation in progress. Land Acquisition for construction of substation building alredy completed. Over all 70 % of work completed Kollam Project HD
15 Nov 2020 Construction of 20LL OHSR at TP site and road restoration works completed ,balance works in progress Kollam Project HD