PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)

Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
Project Code KLMKIIFB0117465
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-Augmentation of WSS in Kollam Corporation PhaseII
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 2350000000
AS Number GO Rt No.14/2017/WRD
TS Amount (Rs) 2350000000
TS Number KWA/CE/(SR)18/2016-17
Total Bill Submitted (Rs) 1480802835
Total Bill Paid (Rs) 1464414610
Population Benefitted 429294
Capacity in MLD 100.00
Actual Project Completion Date 31 Mar 2022
Coverage Kollam Corporation and Kottamkara Panchayath.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I KeralapuramVayanasala Kollam Project Dn
2 Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam Kollam Project Dn
3 Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Othiramughal Kaithacode Kollam Project Dn
4 Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Othiramughal Pavithreswaram Kollam Project Dn
5 Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Pottimukku-Mulavana-Pallimukku Kollam Project Dn
6 Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Puthoor Iverkala Kollam Project Dn
7 Construction of 20LL OHSR at TP site Kollam Project Dn
8 KIIFB - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira. Kollam Project Dn
9 KIIFB - Augmentation of WSS to Kollam Corporation -phase II - Package I - Road restoration work by providing BM & BC at Elampalloor Neeorzhukkil N H road as part of laying 1219 mm dia MS pipe . Kollam Project Dn
10 KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira. Kollam Project Dn
11 KIIFB-WSS to Kollam Corporation - Restoration work of road cut by KWA in Njankadavu Project south Thamarakulam road PWD road general civil work Kollam Project Dn
12 Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode Kollam Project Dn
13 Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Jan 2024 Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- Online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, - Price bid opened on 5/1/2024 and rate quoted is 38% above TPAC and is processing Kollam Project HD
10 Jan 2024 Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- Online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, - Price bid opened on 5/1/2024 and rate quoted is 38% above TPAC and is processing Kollam Project HD
12 Dec 2023 Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- 98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira- Work tendered with due date of opening as 29/9/2023. No offer received. Tender cancelled and Re-tendered with bid submission date on 3/11/2023 and opening on 4/11/2023.No offers were received then extended up to 14/11/2023. No offers received then again extended with submission date 23/11/2023 and opening date 24/11/2023. No offer received again work is extended with submission date 04/12/2023 and opening date 05/12/2023. No offer received again work is extended with submission date 14/12/2023 and opening date 15/12/2023. Kollam Project Dn EE
09 Dec 2023 Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- 98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira- Work tendered with due date of opening as 29/9/2023. No offer received. Tender cancelled and Re-tendered with bid submission date on 3/11/2023 and opening on 4/11/2023.No offers were received then extended up to 14/11/2023. No offers received then again extended with submission date 23/11/2023 and opening date 24/11/2023. No offer received again work is extended with submission date 04/12/2023 and opening date 05/12/2023. No offer received again work is extended with submission date 14/12/2023 and opening date 15/12/2023. Kollam Project Dn EE
07 Dec 2023 Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- 98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira- Work tendered with due date of opening as 29/9/2023. No offer received. Tender cancelled and Re-tendered with bid submission date on 3/11/2023 and opening on 4/11/2023.No offers were received then extended up to 14/11/2023. No offers received then again extended with submission date 23/11/2023 and opening date 24/11/2023. No offer received again work is extended with submission date 04/12/2023 and opening date 05/12/2023. No offer received again work is extended with submission date 14/12/2023 and opening date 15/12/2023. Kollam Project Dn EE

Project Review

See All Review messages
Review Date Review Message Review Attended By
18 Dec 2021 STATUS OF RISK ITEMS TO BE UPDATED AEE
17 Dec 2021 DATA ENTRY TO BE COMPLETED FOR PACKAGES ESPECIALLY PACKAGE 11 AE

Duration & Sanction dates

Date of start of Project 18/04/2018
Scheduled date of Completion of the Project 31 Mar 2022
Expected date of Completion 31/03/2024

Processing Dates

AS Date 11 Jan 2017
TS Date 23 Jan 2017

Other details