Project | PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503) |
---|---|
Project Code | KLMKIIFB0117465 |
Type | Main project |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | KIIFB-Augmentation of WSS in Kollam Corporation PhaseII |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
AS Amount (Rs) | 2350000000 |
AS Number | GO Rt No.14/2017/WRD |
TS Amount (Rs) | 2350000000 |
TS Number | KWA/CE/(SR)18/2016-17 |
Total Bill Submitted (Rs) | 1480802835 |
Total Bill Paid (Rs) | 1464414610 |
Population Benefitted | 429294 |
Capacity in MLD | 100.00 |
Actual Project Completion Date | 31 Mar 2022 |
Coverage | Kollam Corporation and Kottamkara Panchayath. |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I KeralapuramVayanasala | Kollam Project Dn | |
2 | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam | Kollam Project Dn | |
3 | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Othiramughal Kaithacode | Kollam Project Dn | |
4 | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Othiramughal Pavithreswaram | Kollam Project Dn | |
5 | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Pottimukku-Mulavana-Pallimukku | Kollam Project Dn | |
6 | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Puthoor Iverkala | Kollam Project Dn | |
7 | Construction of 20LL OHSR at TP site | Kollam Project Dn | |
8 | KIIFB - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira. | Kollam Project Dn | |
9 | KIIFB - Augmentation of WSS to Kollam Corporation -phase II - Package I - Road restoration work by providing BM & BC at Elampalloor Neeorzhukkil N H road as part of laying 1219 mm dia MS pipe . | Kollam Project Dn | |
10 | KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira. | Kollam Project Dn | |
11 | KIIFB-WSS to Kollam Corporation - Restoration work of road cut by KWA in Njankadavu Project south Thamarakulam road PWD road general civil work | Kollam Project Dn | |
12 | Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode | Kollam Project Dn | |
13 | Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira | Kollam Project Dn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Jan 2024 | Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- Online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, - Price bid opened on 5/1/2024 and rate quoted is 38% above TPAC and is processing | Kollam Project HD | |
10 Jan 2024 | Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- Online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, - Price bid opened on 5/1/2024 and rate quoted is 38% above TPAC and is processing | Kollam Project HD | |
12 Dec 2023 | Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- 98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira- Work tendered with due date of opening as 29/9/2023. No offer received. Tender cancelled and Re-tendered with bid submission date on 3/11/2023 and opening on 4/11/2023.No offers were received then extended up to 14/11/2023. No offers received then again extended with submission date 23/11/2023 and opening date 24/11/2023. No offer received again work is extended with submission date 04/12/2023 and opening date 05/12/2023. No offer received again work is extended with submission date 14/12/2023 and opening date 15/12/2023. | Kollam Project Dn EE | |
09 Dec 2023 | Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- 98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira- Work tendered with due date of opening as 29/9/2023. No offer received. Tender cancelled and Re-tendered with bid submission date on 3/11/2023 and opening on 4/11/2023.No offers were received then extended up to 14/11/2023. No offers received then again extended with submission date 23/11/2023 and opening date 24/11/2023. No offer received again work is extended with submission date 04/12/2023 and opening date 05/12/2023. No offer received again work is extended with submission date 14/12/2023 and opening date 15/12/2023. | Kollam Project Dn EE | |
07 Dec 2023 | Packages 1,3 to 12 100% completed. Package 2-Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira- 98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Package 13, KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira- Work tendered with due date of opening as 29/9/2023. No offer received. Tender cancelled and Re-tendered with bid submission date on 3/11/2023 and opening on 4/11/2023.No offers were received then extended up to 14/11/2023. No offers received then again extended with submission date 23/11/2023 and opening date 24/11/2023. No offer received again work is extended with submission date 04/12/2023 and opening date 05/12/2023. No offer received again work is extended with submission date 14/12/2023 and opening date 15/12/2023. | Kollam Project Dn EE |
Review Date | Review Message | Review Attended By |
---|---|---|
18 Dec 2021 | STATUS OF RISK ITEMS TO BE UPDATED | AEE |
17 Dec 2021 | DATA ENTRY TO BE COMPLETED FOR PACKAGES ESPECIALLY PACKAGE 11 | AE |
Date of start of Project | 18/04/2018 |
---|---|
Scheduled date of Completion of the Project | 31 Mar 2022 |
Expected date of Completion | 31/03/2024 |
AS Date | 11 Jan 2017 |
---|---|
TS Date | 23 Jan 2017 |
Project Officers | View |
---|