Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Jun 2021 Package – 1 - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.14 meters completed. Out of 28130 meters of pipe-laying work 26702.02 meters work completed, Hydro test 23701 m completed. valve chamber works 17 nos. completed out of 40 Nos, air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos. ,(Total 94 % of work completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu – Work in Progress . 30 % work completed. Supply erection and commissioning clear and raw water pump set estimate prepared and submitted to CE for TS approval. Over all 79 % of work completed. Kollam Project HD
02 Jun 2021 Package – 1 - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.14 meters completed. Out of 28130 meters of pipe-laying work 26702.02 meters work completed, Hydro test 23701 m completed. valve chamber works 17 nos. completed out of 40 Nos, air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos. ,(Total 94 % of work completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu – Work in Progress . 40 % work completed. Supply erection and commissioning of clear water and raw water pump sets - Estimate prepared and submitted to CE for TS approval. Over all 79 % of work completed. Kollam Project HD
14 May 2021 Package – 1 - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.14 meters completed. Out of 28130 meters of pipe-laying work 26702.02 meters work completed, Hydro test 23701 m completed. valve chamber works 17 nos. completed out of 40 Nos, air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos. ,(Total 94 % of work completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu – Work in Progress . 29 % work completed. Package IV - Preliminary report of electromechanical work at Njankadavu Intake well and WTP submitted by the consultant was vetted at Head Office and directed to submit the final report. A meeting held on 23.03.2021 with SE & electrical consultant and decided to make some modification to electromechanical work, estimate under preparation. Over all 79 % of work completed. Kollam Project HD
20 Apr 2021 Package – 1 - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15812.41 m completed and 10 mm thick MS pipe 10684.88 meters completed. Out of 28130 meters of pipe-laying work 26497.29 meters work completed, Hydro test 23701 m completed. valve chamber works 15 nos. completed out of 40 Nos, air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos. ,(Total 94 % of work completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu – Work in Progress . 28 % work completed. Package IV - Preliminary report of electromechanical work at Njankadavu Intake well and WTP submitted by the consultant was vetted at Head Office and directed to submit the final report. A meeting held on 23.03.2021 with SE & electrical consultant and decided to make some modification to electromechanical work, estimate under preparation. Over all 79 % of work completed. Kollam Project HD
16 Mar 2021 Package – 1 - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15805.05 m completed and 10 mm thick MS pipe 10481.15 meters completed. Out of 28130 meters of pipe-laying work 26286.20 meters work completed, Hydro test 23701 m completed. valve chamber works 15 nos. completed out of 40 Nos, air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos. ,(Total 93 % completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu – Work in Progress . 914 mm CWGM Laying started at PWD road from Chemmamukk Junction to Manichithod OHSR - Total Pipes Laid =20 Nos. , 914 mm CWGM Laying started at Corporation road from Congress Bhavan to Amala Bakery Junction = Total 7 Nos. Pipes Laid. Package IV - Supply and Erection of transformer and Pump sets – Proposed design by consultancy is submitted to higher authorities for verification. Land Acquisition for construction of substation building already completed. Over all 78 % of work completed. Kollam Project HD
04 Mar 2021 Package – 1 - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15805.05 m completed and 10 mm thick MS pipe 10410.28 meters completed. Out of 28130 meters of pipe-laying work 26215.33 meters work completed, Hydro test 23701 m completed. valve chamber works 15 nos. completed out of 40 Nos, air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos. ,(Total 93 % completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu – Work in Progress 26 % of work completed. Package IV - Supply and Erection of transformer and Pump sets – Proposed design by consultancy is submitted to higher authorities for verification. Land Acquisition for construction of substation building already completed. Over all 77 % of work completed. Kollam Project HD
09 Feb 2021 Package – 1 - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15687.13 m completed and 10 mm thick MS pipe 10410.28 meters completed. Out of 28130 meters of pipe-laying work 26097.41 meters work completed, Hydro test 23701 m completed. valve chamber works 15 nos. completed out of 40 Nos, air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos. ,(Total 92 % completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu – Work in Progress. Package IV - Supply and Erection of transformer and Pump sets – Proposed design by consultancy is submitted to higher authorities for verification. Land Acquisition for construction of substation building already completed. Over all 76 % of work completed. Kollam Project HD
01 Feb 2021 Package – 1 - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15278.94 m completed and 10 mm thick Ms pipe 10410.28 meters completed. Out of 28130 meters of pipe-laying work 25689.22 meters work completed. Hydro test 22855.89 m completed. RCC pipe bridgework in progress. valve chamber works 15 nos. completed out of 40 Nos, air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos. ,(90 % completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu - 26 % completed. Package IV - Supply and Erection of transformer and Pump sets – Proposed design by consultancy is submitted to higher authorities for verification . Land Acquisition for construction of substation building already completed. Over all 75 % of work completed. Kollam Project HD
11 Jan 2021 Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 25208.88 meters completed,(90 % completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu - 26 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded, Estimate and Design submitted on 10/01/2021. Land Acquisition for construction of substation building already completed. Over all 74 % of work completed. Kollam Project HD
10 Dec 2020 Package 1- Laying of raw water pumping main out of 28130 meter of pipe line laying work 24352.39 meters completed, Package II - Construction of 20 LL OHSR at Vasoorichira Work Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu - 25 % completed. Package IV - Supply and Erection of transformer and Pump sets - Work of design consultancy awarded, Estimate preparation in progress. Land Acquisition for construction of substation building already completed. Over all 73 % of work completed. Kollam Project HD