03 Nov 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira – Application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal. Package X - 914 mm gravity main – 5479.845 m laid out of 6130m,1016 mm clear water pumping main - 3617.46 mm laid out of 3835m. Hydrotesting of pipelines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber works- 10 Nos completed 6 Nos balance. Cathodic protection work in progress. The whole plastering work of 54LL OHSR at Manichithodu was completed and the Painting work was completed. The casting of the top beam of the pipeline bridge at kallupalam was completed on both sides. The casting of the pipeline bridge at Ayathil is completed and pipe laying through the pipeline bridge is completed. Pit for railway Push through work 75% completed. Kallupalam pipeline bridge fabrication work in progress. Handrail fixing work is in progress at 54LL OHSR at Manichithodu Package XI- TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022.No offers were received then extended upto 12/09/2022.Since no offers were received, the work will be retendered with submission date 1-10-2022 and opening date 3-10-2022. One offer received. Technical bid submitted to CE(SR) for pre-qualification on 12/10/2022. Pre-qualification Minutes received on 21/10/2022.Final Pre-qualification is under processing. Price bid opened on 3/10/2022.One offer received, Quated rate 36% above the TPAC. Package XII- Tenders of packages V and VII opened on 4/5/2022. No offers were received hence the tenders were extended up to 16/05/2022. again no offer was received then again tender was extended up to 26/05/2022.no offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers were received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022. Tender cancelled due to no participation. Package VIII, tender sanctioned from CE's office.But the tender for transformer building is not taken by any bidders,the tender for automation and solar panel is cancelled. Estimate recating of pumpsets and automation,solar panel etc is going on. Kollam Project HD
01 Nov 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira – Application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal. Package X - 914 mm gravity main – 5474.075 m laid out of 6130m,1016 mm clear water pumping main - 3617.46 mm laid out of 3835m. Hydrotesting of pipelines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber works- 10 Nos completed 6 Nos balance. Cathodic protection work in progress. The whole plastering work of 54LL OHSR at Manichithodu was completed and the Painting work was completed. The casting of the top beam of the pipeline bridge at kallupalam was completed on both sides. The casting of the pipeline bridge at Ayathil is completed and pipe laying through the pipeline bridge is completed. Pit for railway Push through work 75% completed. Kallupalam pipeline bridge fabrication work in progress. Handrail fixing work is in progress at 54LL OHSR at Manichithodu Package XI-KIIFB - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira.- TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022.No offers were received then extended upto 12/09/2022.Since no offers were received, the work will be retendered with submission date 1-10-2022 and opening date 3-10-2022. One offer received. Technical bid submitted to CE(SR) for pre-qualification on 12/10/2022. Pre-qualification Minutes received on 21/10/2022.Final Pre-qualification under processing. Package XII- Tenders of packages V and VII opened on 4/5/2022. No offers were received hence the tenders were extended up to 16/05/2022. again no offer was received then again tender was extended up to 26/05/2022.no offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers were received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022. Tender cancelled due to no participation. Package VIII, tender sanctioned from CE's office.But the tender for transformer building is not taken by any bidders,the tender for automation and solar panel is cancelled. Estimate recating of pumpsets and automation,solar panel etc is going on. Kollam Project HD
29 Oct 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira – Application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal. Package X - 914 mm gravity main – 914 mm gravity main – 5413.185m laid out of 6130m ,1016 mm clear water pumping main - 3617.46 mm laid out of 3835m. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber work 10 Nos completed, 6 Nos balance. Cathodic protection work in progress . Whole plastering work of 54LL OHSR at Manichithodu was completed and Painting work completed. Concreting of top beam of pipe line bridge at kallupalam was completed on both sides. Concreting for pipe line bridge at Ayathil is completed and pipe laying through the pipe line bridge completed. Pit for railway Push through work 75% completed. Kallupalam fabrication work in progress. . Package XI-KIIFB - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira.- TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022.No offers were received then extended upto 12/09/2022.Since no offers were received, the work will be retendered with submission date 1-10-2022 and opening date 3-10-2022. One offer received. Technical bid submitted to CE(SR) for pre-qualification on 12/10/2022. Package XII- Tenders of packages V and VII opened on 4/5/2022. No offers were received hence the tenders were extended up to 16/05/2022. again no offer was received then again tender was extended up to 26/05/2022.no offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers were received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022. Tender cancelled due to no participation. Package VIII, tender sanctioned from CE's office.But the tender for transformer building is not taken by any bidders,the tender for automation and solar panel is cancelled.Estimate recating of pumpsets and automation,solar panel etc is going on. Kollam Project HD
16 Oct 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira – Application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal. Package X - 914 mm gravity main – 914 mm gravity main – 5413.185m laid out of 6130m ,1016 mm clear water pumping main - 3617.46 mm laid out of 3835m. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber work 10 Nos completed, 6 Nos balance. Cathodic protection work in progress . Whole plastering work of 54LL OHSR at Manichithodu was completed and Painting work completed. Concreting of top beam of pipe line bridge at kallupalam was completed on both sides. Concreting for pipe line bridge at Ayathil is completed and pipe laying through the pipe line bridge completed. Pit for railway Push through work 75% completed. Kallupalam fabrication work in progress. . Package XI-KIIFB - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira.- TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022.No offers were received then extended upto 12/09/2022.Since no offers were received, the work will be retendered with submission date 1-10-2022 and opening date 3-10-2022. One offer received. Technical bid submitted to CE(SR) for pre-qualification on 12/10/2022. Package XII- Tenders of packages V and VII opened on 4/5/2022. No offers were received hence the tenders were extended up to 16/05/2022. again no offer was received then again tender was extended up to 26/05/2022.no offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers were received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022. Tender cancelled due to no participation. Package VIII, tender sanctioned from CE's office.But the tender for transformer building is not taken by any bidders,the tender for automation and solar panel is cancelled. Kollam Project Dn EE
10 Oct 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira – Application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal. Package X - 914 mm gravity main – 5377.655 m laid out of 6130m ,1016 mm clear water pumping main - 3617.46 mm laid out of 3835m. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber work 10 Nos completed, 6 Nos balance. Cathodic protection work in progress . Whole plastering work of 54LL OHSR at Manichithodu was completed and Painting work progressing. Concreting of top beam of pipe line bridge at kallupalam was completed on both sides. Concreting of T- Beam for pipe line bridge at Ayathil is completed and Cover slab(flange of T beam) concrete completed. Pit for railway Push through work 75% completed. Kallupalam fabrication work in progress. Package XI-KIIFB - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira.- TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022.No offers were received then extended upto 12/09/2022.Since no offers were received, the work will be retendered with submission date 1-10-2022 and opening date 3-10-2022.One offer received. Prequalification under processing. Package XII- Tenders of packages V and VII opened on 4/5/2022. No offers were received hence the tenders were extended up to 16/05/2022. again no offer was received then again tender was extended up to 26/05/2022.no offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers were received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022. Tender cancelled due to no participation. Package VIII, tender sanctioned from CE's office.But the tender for transformer building is not taken by any bidders,the tender for automation and solar panel is cancelled. Kollam Project Dn AE
02 Oct 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira – Application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal. Package X - 914 mm gravity main – 5360.415 m laid out of 6130m ,1016 mm clear water pumping main - 3146.135m laid out of 3835m. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber work 10 Nos completed, 6 Nos balance. Cathodic protection work in progress . Whole plastering work of 54LL OHSR at Manichithodu was completed and Painting work progressing. Concreting of top beam of pipe line bridge at kallupalam was completed on both sides. Concreting of T- Beam for pipe line bridge at Ayathil is completed and Cover slab(flange of T beam ) concrete completed. Pit for railway Push through work 75% completed. Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. - STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022. No offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022. Tender cancelled due to no participation. Package VIII, tender sanctioned from CE's office and Seeking firm period extension from contractor from SE’s office. Package XII- Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira - Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 and extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. Retender was due on 16/04/2022. No offers were received and hence tender was cancelled and revised estimate was submitted for revised TS. TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022. Kollam Project HD
01 Sep 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira – Application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal. Package X - 914 mm gravity main – 5360.415 m laid out of 6130m ,1016 mm clear water pumping main - 3146.135m laid out of 3835m. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber work 10 Nos completed, 6 Nos balance. Cathodic protection work in progress . Whole plastering work of 54LL OHSR at Manichithodu was completed and Painting work progressing. Concreting of top beam of pipe line bridge at kallupalam was completed on both sides. Concreting of T- Beam for pipe line bridge at Ayathil is completed and Cover slab(flange of T beam ) concrete completed. Pit for railway Push through work 75% completed. Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. - STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022. No offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022. Tender cancelled due to no participation. Package VIII, tender sanctioned from CE's office and Seeking firm period extension from contractor from SE’s office. Package XII- Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira - Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 and extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. Retender was due on 16/04/2022. No offers were received and hence tender was cancelled and revised estimate was submitted for revised TS. TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022. Kollam Project HD
22 Aug 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira - Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. Total HYDROTEST 26035.87 meter Completed. 510 M Road concreting and Leak rectification work completed at nanthirikkal. Road restoration work completed at Pazhavara. Road Restoration work completed at (Coporation road) Punathalathazham – Vasoorichira WTP site. Package X - Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHSR at Manichithode, 914 mm gravity main – 5360.415 m laid out of 6130m ,1016 mm clear water pumping main - 3120.955m laid out of 3835m. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber work 10 Nos completed, 6 Nos balance. Cathodic protection work in progress . Whole plastering work of 54LL OHSR at Manichithodu was completed and Painting work progressing. Concreting of top beam of pipe line bridge at kallupalam was completed on both sides. Concreting of T- Beam for pipe line bridge at Ayathil is completed and Cover slab(flange of T beam ) concrete completed. Pit for railway Push through work 75% completed. Package XI - Augmentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. - STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022. No offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022.Package VIII, tender sanctioned from CE's office and Seeking firm period extension from contractor from SE’s office. Package XII- Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira - Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 and extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. Retender was due on 16/04/2022. No offers were received and hence tender was cancelled and revised estimate was submitted for revised TS. TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022. Kollam Project HD
21 Aug 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira - Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. Total HYDROTEST 26035.87 meter Completed. 510 M Road concreting and Leak rectification work completed at nanthirikkal. Road restoration work completed at Pazhavara. Road Restoration work completed at (Coporation road) Punathalathazham – Vasoorichira WTP site. Package X - Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHSR at Manichithode, 914 mm gravity main – 5360.415 m laid out of 6130m ,1016 mm clear water pumping main - 3120.955m laid out of 3835m. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber work 10 Nos completed, 6 Nos balance. Cathodic protection work in progress . Whole plastering work of 54LL OHSR at Manichithodu was completed and Painting work progressing. Concreting of top beam of pipe line bridge at kallupalam was completed on both sides. Concreting of T- Beam for pipe line bridge at Ayathil is completed and Cover slab(flange of T beam ) concrete completed. Pit for railway Push through work 75% completed. Package XI - Augmentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. - STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022. No offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022.Package VIII, tender sanctioned from CE's office and Seeking firm period extension from contractor from SE’s office. Package XII- Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira - Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 and extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. Retender was due on 16/04/2022. No offers were received and hence tender was cancelled and revised estimate was submitted for revised TS. TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022. Kollam Project HD
18 Aug 2022 Packages I to III & V to IX - Work Completed 100%. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira - Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. Total HYDROTEST 26035.87 meter Completed. 510 M Road concreting and Leak rectification work completed at nanthirikkal. Road restoration work completed at Pazhavara. Road Restoration work completed at (Coporation road) Punathalathazham – Vasoorichira WTP site. Package X - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira - Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 and extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. Retender was due on 16/04/2022. No offers were received and hence tender was cancelled and revised estimate was submitted for revised TS. TS issued by CE(SR)on 07/07/22 .Work tendered with submission date 4-8-2022 and opening date 6-8-2022. Since no offers were received, the work will be retendered with submission date 3-9-2022 and opening date 5-9-2022.Package XI - Augmentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. - STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022. No offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.No offers received then again extended up to 20/07/2022. No offers were received then again extended up to 29/07/2022. But No offers were received then again extended up to 16/08/2022. No offers received then again extended up to 26/08/2022.Package VIII, tender sanctioned from CE's office and Seeking firm period extension from contractor from SE’s office. Package XII - Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHSR at Manichithode, 914 mm gravity main – 5360.415 m laid out of 6130m ,1016 mm clear water pumping main - 3120.955m laid out of 3835m. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Valve chamber work 10 Nos completed, 6 Nos balance. Cathodic protection work in progress . Whole plastering work of 54LL OHSR at Manichithodu was completed and Painting work progressing. Concreting of top beam of pipe line bridge at kallupalam was completed on both sides. Concreting of T- Beam for pipe line bridge at Ayathil is completed and Cover slab(flange of T beam ) concrete completed. Pit for railway Push through work 75% completed. Kollam Project HD