Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Jul 2022 Package I-III & V–IX - Work Completed 100%.Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira - Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work were completed. Cathodic protection work (70% completed) is in progress. Package X - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira - Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 and extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. Retender was due on 16/04/2022. No offers were received and hence tender was cancelled and estimate is given for revised estimate. Package XI - Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode 914 mm gravity main - Laying Total 5360.415 m out of 6130m completed,1016 mm clear water pumping main laying work 3120.955m completed out of 3835m. Plastering work of 54LL OHSR at manichithode – 90% completed. Hydrotesting of pipelines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Package XII - Augmentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. - STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022. No offers were received then again extended up to 16/06/2022 . No offers were received then again extended up to 27/06/2022. No offers were received then again extended up to 8/07/2022.Package VIII, tender sanctioned from CE's office. Package VIII, tender sanctioned from CE's office. Kollam Project HD
02 Jun 2022 1) Package I-III & V–IX - Work Completed 100%. 2)Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira - Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work were completed. Cathodic protection work (70% completed) is in progress. 3) Package X - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira - Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 and extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. 4) Package XI - Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode 914 mm gravity main - Laying Total 5360.415 m out of 6130m completed,1016 mm clear water pumping main laying work 3120.955m completed out of 3835m. Plastering work of 54LL OHSR at manichithode – 90% completed. Hydrotesting of pipelines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. 5) Package XII - Augmentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. - STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022 Package VIII, tender sanctioned from CE's office. Kollam Project HD
01 Jun 2022 1) Package I-III & V–IX - Work Completed 100%. 2)Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira - Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work were completed. Cathodic protection work (70% completed) is in progress. 3) Package X - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira - Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 and extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. 4) Package XI - Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode 914 mm gravity main - Laying Total 5360.415 m out of 6130m completed,1016 mm clear water pumping main laying work 3120.955m completed out of 3835m. Plastering work of 54LL OHSR at manichithode – 90% completed. Hydrotesting of pipelines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. 5) Package XII - Augmentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. - STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022 Package VIII, tender sanctioned from CE's office. Kollam Project HD
01 Jun 2022 1) Package I-III & V–IX - Work Completed 100%. 2)Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. Road concreting work on pazhavara – NSS karayogam road completed. BM & BC Road work Completed from Punthalathazham to vasoorichira. The scour valve fixing work at kanjiracodu is completed from punthalathazham to Vasoorichira . The scour valve fixing work at kanjirakodu is completed. Scour valve chamber concrete work completed at ayirikuzhi , kanjirakodu and nanthirikkal. Thrust block and pipe protecting concrete work completed at kanjirakodu. Exacavation of trenches at scour site njankadavu started for laying and completing the gap near intake well. Lifted air valve setting at mulavana completed. Cathodic protection work (70% completed) is in progress.3) Package X - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira. Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. 4) Package XI - Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode 914 mm gravity main - Laying Total 5360.415 m out of 6130m completed,1016 mm clear water pumping main laying work 3120.955m completed out of 3835m. Tie beam and column work of pipe bridge at Kallupalam in progress. Plastering work of 54LL OHSR at manichithode – 90% completed. Road work up to WMM completed at DCC office. Hydrotesting of pipelines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Air valve chamber work and Cathodic protection work are in progress. 6 nos piling work completed at Aythil pile load test progressing. Valve chamber work started at the civil station. Concreting of beam of pipe bridge at kallupalam completed. 5) Package XII - Augmentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022 Package VIII, tender sanctioned from CE's office. Kollam Project HD
01 Jun 2022 •Package I-III & V–IX - Work Completed 100%. •Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe-laying work 26870.50 meters of work completed. Road concreting work on pazhavara – NSS karayogam road completed. BM & BC Road work Completed from Punthalathazham to vasoorichira. The scour valve fixing work at kanjiracodu is completed from punthalathazham to Vasoorichira . The scour valve fixing work at kanjirakodu is completed. Scour valve chamber concrete work completed at ayirikuzhi , kanjirakodu and nanthirikkal. Thrust block and pipe protecting concrete work completed at kanjirakodu. Exacavation of trenches at scour site njankadavu started for laying and completing the gap near intake well. Lifted air valve setting at mulavana completed. Cathodic protection work (70% completed) is in progress. •Package X - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lakeshore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira. Work tendered twice. Received single bid offer. Tender scrutinized at SE office and submitted to C.E on 12/01/2022. On 27/01/2022 C.E prequalified the tender. The awarded work amount was 8.5% above TPAC. However, as the quoted rate was 43.8% above TPAC, the tender was cancelled. Hence it was retendered with due date of 17/03/2022 extended up to 24/03/2022, then to 5/4/2022 and 13/4/2022. However, no offers were received. •Package XI - Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode 914 mm gravity main - Laying Total 5360.415 m out of 6130m completed,1016 mm clear water pumping main laying work 3120.955m completed out of 3835m. Tie beam and column work of pipe bridge at Kallupalam in progress. Plastering work of 54LL OHSR at manichithode – 90% completed. Road work up to WMM completed at DCC office. Hydrotesting of pipelines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Air valve chamber work and Cathodic protection work are in progress. 6 nos piling work completed at Aythil pile load test progressing. Valve chamber work started at the civil station. Concreting of beam of pipe bridge at kallupalam completed. •Package XII - Augmentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation. STC directed to re-tender the work by splitting the estimate to get better competition. In this regard, the work was split up into 3 packages. Tenders of packages V and VII opened on 4/5/2022. No offers were received. Hence the tenders extended up to 16/05/2022. Again no offer was received. Again tender was extended up to 26/05/2022. No offers were received and then again extended up to 08/06/2022 Package VIII, tender sanctioned from CE's office. Kollam Project HD
30 May 2022 Package I - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package II – Augmentation of Water Supply Scheme to Kollam Corporation , Othiramughal pavithreswaram (Road restoration work ) - Work 100 % Completed. Package III Augmentation of Water Supply Scheme to Kollam Corporation (Road restoration work ) - Pttimukku – Mulavana –Pallimukku - Work 100 % Completed. Package IV - Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira - Total laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10951.37 meters completed. Out of 28130 meters of pipe laying work 26870.50 meters of work completed. Road concreting work on pazhavara – NSS karayogam road completed . BM & BC Road work Completed from Punthalathazham to vasoorichira. The scour valve fixing work at kanjiracodu is completed from punthalathazham to Vasoorichira . The scour valve fixing work at kanjirakodu is completed. Scour valve chamber concrete work completed at ayirikuzhi , kanjirakodu and nanthirikkal. Thrust block and pipe protecting concrete work completed at kanjirakodu. Exacavation of trenches at scour site njakadav started for laying and completing the gap near intake well. Lifted airvalve setting at mulavana completed. Cathodic protection work (70% completed) in progress. Package V - Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration work - Kuttichira thattarkonam - work 100 % completed. Package VI Augmentation of WSS to Kollam Corporation -phase II - Road restoration work BM & BC at Elampalloor Neeorzhukkil N H road as part of laying 1219 mm dia MS pipe – work 100 % completed. Package VII Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration work - Keralapuram- Vayanasala - work 100 % completed. Package VIII Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration work- Othiramughal – Kaithacode work 100 % completed. Package IX Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration work Puthoor – Iverkala work 100 % completed. Package X KIIFB - Augmentation of Kollam corporation - Phase l - Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira. STC directed to re- tender the work by splitting the estimate for get better competition. In this regard the work was spilt-up in to 3 packages. Tenders of package V and VII opened on 4/5/2022. No offers received hence the tenders extended up to 16/05/2022. again no offer received then again tender extended up to 26/05/2022.no offers recieved then again extrended up to 08/06/2022 Package VIII, tender sanctioned from CE's office. Package XI Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode - 914 mm gravity main - Laying Total 5360.415 m out of 6130m completed,1016 mm clear water pumping main laying work 3120.955m completed out of 3835m. Tie beam and column work of pipe bridge at Kallupalam in progress. Plastering work of 54LL OHSR at manichithode – 90% completed. Road work up to WMM completed at DCC office. Hydrotesting of pipe lines - 914 mm- 5046.2m completed, 1016mm - 2944m completed. Air valve chamber work and Cathodic protection work in progress. 6 nos piling work completed at Aythil pile load test progressing.Valve chamber work started at civil station . Concreting of beam of pipe bridge at kallupalam completed. Package XII Tenders of package V and VII opened on 4/5/2022.No offers received hence the tenders extended up to 16/05/2022. again no offer received then again tender extended up to 26/05/2022. Package VIII, tender sanctioned from CE's office. Kollam Project HD
23 Mar 2022 Package (1) Valve chamber works, Road restoration works are in progress at corporation and Panchayth roads .Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. Total HYDROTEST 26035.87 METER COMPLETED. 7 Nos. Scour valve chamber work completed and 21 nos Air valve chamber work completed.Total 96 % of work completed. BM & BC Road work Completed from Punthalathazham to vasoorichira. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - Pumping main 2940 m out of 3835 m completed, Gravitymain 4777 m out of 6130 m completed. OHSR roof slab 100% completed overall 70% of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - work retendered with due date on 21/2/2022. Single bid recieved.PQ processing at SE office. Tender cancelled and Re-Tender invited by spliting up the components. The costruction of substation building, retaining wall, approach road in Pachage 5 is retendererd with due date 5/01/2022 , single bid received. Selection notice issued .Contractor not willing to accept, hence retendered with due date as on 17-03-2022. Since no offer received, due date extended. Overall 82 % of work completed. Kollam Project HD
16 Mar 2022 Package (1) Valve chamber works, Road restoration works are in progress at corporation and Panchayth roads .Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. Total HYDROTEST 26035.87 METER COMPLETED. 7 Nos. Scour valve chamber work completed and 21 nos Air valve chamber work completed.Total 96 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - Pumping main 2940 m out of 3835 m completed, Gravitymain 4544 m out of 6130 m completed. OHSR roof slab 100% completed overall 68% of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - work retendered with due date on 21/2/2022. Single bid recieved.PQ processing at SE office.The costruction of substation building, retaiing wall, approach road in Pachage 5 is retendererd with due date 5/01/2022 , single bid received. Selection notice issued .Contractor not willing to accept, hence retendered with due date as on 17-03-2022. Overall 82 % of work completed Kollam Project Dn AE
01 Mar 2022 Package (1) Valve chamber works, Road restoration works are in progress at corporation and Panchayth roads .Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. Total HYDROTEST 26035.87 METER COMPLETED. 7 Nos. Scour valve chamber work completed and 21 nos Air valve chamber work completed.Total 96 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - Pumping main 2940 m out of 3835 m completed, Gravitymain 4267 m out of 6130 m completed. OHSR roof slab 60% completed overall 65% of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - work retendered with due date on 21/2/2022. Single bid recieved.PQ processing at SE office.The costruction of substation building, retaiing wall, approach road in Pachage 5 is retendererd with due date 5/01/2022 , single bid received. Selection notice issued .Contractor not willing to accept, hence retendered with due date as on 17-03-2022. Overall 82 % of work completed Kollam Project HD
15 Feb 2022 Package (1) Valve chamber works, Road restoration works are in progress at corporation and Panchayth roads .Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. Total HYDROTEST 26035.87 METER COMPLETED. 7 Nos. Scour valve chamber work completed and 21 nos Air valve chamber work completed.Total 96 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - Pumping main 2251 out of 3835 m completed, Gravitymain 4070 m out of 6130 m completed. OHSR roof slab 60% completed overall 60% of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - work retendered with due date on 21/2/2022. The costruction of substation building, retaiing wall, approach road in Pachage 5 is retendererd with due date 5/01/2022 , single bid received. price bid submitted to CE . Overall 82 % of work completed Kollam Project HD