Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Feb 2022 Package (1) Valve chamber works, Road restoration works are in progress at corporation and Panchayth roads .Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. Total HYDROTEST 26035.87 METER COMPLETED. 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed.Total 96 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - Pumping main 2251 out of 3835 m completed, Gravitymain 4070 m out of 6130 m completed. OHSR roof slab 60% completed overall 60% of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - work retendered with due date on 21/2/2022. The costruction of substation building, retaiing wall, approach road in Pachage 5 is retendererd with due date 5/01/2022 , single bid received. price bid submitted to CE . Overall 82 % of work completed Kollam Project HD
13 Jan 2022 Package (1) Valve chamber works, Road restoration works are in progress at corporation and Panchayth roads .Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. Total HYDROTEST 26035.87 METER COMPLETED. 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed.Total 96 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - Pumping main 1109 m completed, Gravitymain 4070 m completed. 56% of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - work tendered with due date on 22/01/22. The costruction of substation building, retaiing wall, approach road in Pachage 5 is retendererd with due date 5/01/2022 , single bid received. tender evaluation progress at Se office. Overall 82 % of work completed Kollam Project HD
13 Jan 2022 Package (1) Valve chamber works, Road restoration works are in progress at corporation and Panchayth roads .Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. Total HYDROTEST 26035.87 METER COMPLETED. 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed.Total 96 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - Pumping main 1008 m completed, Gravitymain 4072 m completed. 56% of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - work tendered with due date on 22/01/22. The costruction of substation building, retaiing wall, approach road in Pachage 5 is retendererd with due date 5/01/2022 , single bid received. tender evaluation progress at Se office. Overall 82 % of work completed Kollam Project HD
20 Dec 2021 Package (1) Valve chamber works, Road restoration works are in progress at corporation and Panchayth roads .Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. Total HYDROTEST 26035.87 METER COMPLETED. 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed.Total 96 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - 53% of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - The revised estimate as per direction of CE submitted and directed to revise the estimate based on revised design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). The costruction of substation building, retaiing wall, approach road in Pachage 5 is tendeder twice and due date is on 5/1/2022. Overall 81 % of work completed Kollam Project HD
18 Nov 2021 Package (1) Laying works are in progress at Nanthirikkal Panchayath road.Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. 22 th hydrotest completed . Total HYDROTEST 26035.87 METER COMPLETED. 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed.Total 96 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - 37 % of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - The estimate return by CE and directed to revise the estimate and re design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). Also as per the existing rules of KWA if the Capacity of C F pump set is more than 200 HP it is necessary to provide H T connection. As per the new IS Code it is better to provide energy efficiency motors having LT connections. Hence clarification from higher authorities is required the same has been intimated to CE for getting sanction from Higher Authorities. Overall 81 % of work completed Kollam Project HD
14 Sep 2021 Package (1) Laying works are in progress at Nanthirikkal Panchayath road.Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10897 meters completed. Out of 28130 meters of pipe-laying work 26816.13 meters of work completed. 22 th hydrotest completed . Total HYDROTEST 26035.87 METER COMPLETED. 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed.Total 95 % of work completed. Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - 37 % of work completed. Package IV Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - The estimate return by CE and directed to revise the estimate and re design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). Also as per the existing rules of KWA if the Capacity of C F pump set is more than 200 HP it is necessary to provide H T connection. As per the new IS Code it is better to provide energy efficiency motors having LT connections. Hence clarification from higher authorities is required the same has been intimated to CE for getting sanction from Higher Authorities. Overall 81 % of work completed Kollam Project HD
25 Aug 2021 Package – 1 – Gap closing works are in progress. Total HYDROTEST 26035.87 METER COMPLETED. 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed. Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10811.14 meters completed. Out of 28130 meters of pipe-laying work 26730.27 meters of work completed. Air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos.,(Total 95 % of work completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - 33 % of work completed. Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - The estimate return by CE and directed to revise the estimate and re design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). Also as per the existing rules of KWA if the Capacity of C F pump set is more than 200 HP it is necessary to provide H T connection. As per the new IS Code it is better to provide energy efficiency motors having LT connections. Hence clarification from higher authorities is required the same has been intimated to CE for getting sanction from Higher Authorities. Overall 80 % of work completed Kollam Project HD
25 Aug 2021 Package – 1 – Gap closing works are in progress. Total HYDROTEST 26035.87 METER COMPLETED. 5 Nos. Scour valve chamber work completed and 16 nos Air valve chamber work completed. Total Laying of 1219 mm dia MS pipe 12.50 mm thickness 15919.13 m completed and 10 mm thick MS pipe 10811.14 meters completed. Out of 28130 meters of pipe-laying work 26730.27 meters of work completed. Air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos.,(Total 95 % of work completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - 33 % of work completed. Supply,erection,commissioning and maintaining of Clear Water & Raw water pump sets and Electrical Sub stations at TP site - The estimate return by CE and directed to revise the estimate and re design the Raw water pump set incorporating the demand of 4 panchayath (Perinadu, Thrikkaruva,Panayam and Mandrothuruth). Also as per the existing rules of KWA if the Capacity of C F pump set is more than 200 HP it is necessary to provide H T connection. As per the new IS Code it is better to provide energy efficiency motors having LT connections. Hence clarification from higher authorities is required the same has been intimated to CE for getting sanction from Higher Authorities. Kollam Project HD
25 Jul 2021 Package – 1 – Gap closing works are in progress - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.14 meters completed. Out of 28130 meters of pipe-laying work 26706.02 meters work completed, Hydro test 23701 m completed. Valve chamber works 19 nos. completed (Construction of Scour valve chamber work 4 nos completed and Air valve chamber 15 Nos Completed) out of 40 Nos, Air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos.,(Total 94 % of work completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - 33 % of work completed. Supply erection and commissioning clear and raw water and clear water pump set estimate prepared and submitted to CE for TS approval. Over all 80 % of work completed. Kollam Project HD
06 Jul 2021 Package – 1 – Gap closing works are in progress - Laying of 1219 mm dia MS pipe 12.50 mm thickness 15894.88 m completed and 10 mm thick MS pipe 10811.14 meters completed. Out of 28130 meters of pipe-laying work 26706.02 meters work completed, Hydro test 23701 m completed. Valve chamber works 19 nos. completed (Construction of Scour valve chamber work 4 nos completed and Air valve chamber 15 Nos Completed) out of 40 Nos, Air valve 31 Nos Supply completed, Scour valve 9 nos. supply completed out of 15 Nos.,(Total 94 % of work completed). Package II - Construction of 20 LL OHSR at Vasoorichira Work 100 % Completed. Package III - laying clear water pumping main and gravity main, Construction of 54 LL OHSR at Manichithodu–Work in Progress - 33 % of work completed. Supply erection and commissioning clear and raw water and clear water pump set estimate prepared and submitted to CE for TS approval. Over all 80 % of work completed. Kollam Project HD