| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Feb 2022 | Equilization tank sump portion PCC completed on 9.02.2022 .. MBBR no.1 excavation completed and leveling works in progress..CCT wall shutter making in progress | Kollam Project HD | |
| 09 Feb 2022 | MBBR IV first lift wall curing work in progress..clarifier 2 wall shutter making work in progress.. equilization tank sump ready for pcc...CCT wall shutter making work in progress... | Kollam Project HD | |
| 08 Feb 2022 | MBBR IV...curing progress..equilization tank ..earth levelling ..clarifier no 2 ..wall shutter making progress...MBBR I ..earth excavation progress... | Kollam Project HD | |
| 07 Feb 2022 | MBBR IV RCC side wall upto a height of 2.4m completed on 5.02.2022 and excavation works for equilization tank completed & leveling for pcc in progress..MBBR IV wall curing works in progress..MBBR I earth excavation works in progress.. | Kollam Project HD | |
| 06 Feb 2022 | MBBR IV RCC side wall upto a height of 2.4m completed on 5.02.2022 and excavation works for equilization tank completed & leveling for pcc in progress | Kollam Project HD | |
| 04 Feb 2022 | Equilization tank earth excavation works in progress ..MBBR IV.. ready for concrete ..MBBR III reinforcement work. | Kollam Project HD | |
| 03 Feb 2022 | MBBR IV wall form work completed ..ready for concrete..equilization tank excavation works in progress.. chlorine room slab deshuttering completed.. MBBR III reinforcement works in progress.. | Kollam Project HD | |
| 02 Feb 2022 | Equilization tank excavation works and mbbr iv shuttering in progress…secondary clarifier no 1 and 2 curing progress.. | Kollam Project HD | |
| 01 Feb 2022 | Equilization tank earth excavation works in progress.. MBBR IV out side wall form work.. CCT inner wall starter formwork.. secondary clarifier 1 and 2 curing work progress.. Chlorine room slab deshuttering work. | Kollam Project HD | |
| 29 Jan 2022 | work for secondary clarifier no.1 RCC work completed…Curing progress ..excavation of equilization tank in progress.. MBBR IV inside shutter work progress | Kollam Project HD |