| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Mar 2022 | Equilization Raft reinforcement work in progress..., Clarifier - I Side wall reinforcement & form work in progress...,CCT inner wall form work in progress... | Kollam Project HD | |
| 03 Mar 2022 | MBBR - I & II Getting ready for Raft RCC, Equilization Tank raft reinforcement work in progress..., CCT Outside shuttering work in progress..., Clarifier - II 1st lift wall reinforcement work in progress... | Kollam Project HD | |
| 01 Mar 2022 | MBBR no.3 raft completed on 28.02.2022. , EQUILIZATION tank sump portion Raft completed on 1.3.2022. MBBR no.1 reinforcement completed for raft…MBBR no.2 reinforcement work for raft in final stage. Chlorine room block work completed and ready for plastering. Equilization tank sump portion reinforcement completed. CCT reinforcement work completed and form work in final stage | Kollam Project HD | |
| 01 Mar 2022 | MBBR 3 Raft RCC completed. | Kollam Project Dn EE | |
| 01 Mar 2022 | Equilization Tank Raft reinforcement work in progress..., CCT inner wall form work in progress... | Kollam Project HD | |
| 28 Feb 2022 | MBBR I & II Raft reinforcement work in progress..., CCT wall form work in progress..., Chlorine room wall outside plastering work started | Kollam Project HD | |
| 26 Feb 2022 | Sludge Thickner & Pre-treatment unit Earth excavation in progress..., CCT 1st lift wall inside form work in progress..., MBBR - 1& 2 Raft reinforcement work in progress. | Kollam Project HD | |
| 25 Feb 2022 | Sludge Thickner - Earth excavation in progress..., CCT 1st lift wall inside form work in progress..., MBBR - 1& 2 Raft reinforcement work in progress...,MBBR - 3 Raft reinforcement work completed .... | Kollam Project HD | |
| 24 Feb 2022 | second lot epoxy coated steel arrived at site on 20/2/2022 and reinforcement works of all components started and in good progress. Raft RCC of MBBR no.3, Equilization tank sump portion is proposed on 25.02.2022 | Kollam Project HD | |
| 23 Feb 2022 | Sludge Thickener - Earth excavation in progress..., CCT 1st lift wall inside form work in progress..., MBBR - III & II Raft reinforcement work in progress..., Chlorine room block work in progress... | Kollam Project HD |