Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Mar 2022 Equilization Raft reinforcement work in progress..., Clarifier - I Side wall reinforcement & form work in progress...,CCT inner wall form work in progress... Kollam Project HD
03 Mar 2022 MBBR - I & II Getting ready for Raft RCC, Equilization Tank raft reinforcement work in progress..., CCT Outside shuttering work in progress..., Clarifier - II 1st lift wall reinforcement work in progress... Kollam Project HD
01 Mar 2022 MBBR no.3 raft completed on 28.02.2022. , EQUILIZATION tank sump portion Raft completed on 1.3.2022. MBBR no.1 reinforcement completed for raft…MBBR no.2 reinforcement work for raft in final stage. Chlorine room block work completed and ready for plastering. Equilization tank sump portion reinforcement completed. CCT reinforcement work completed and form work in final stage Kollam Project HD
01 Mar 2022 MBBR 3 Raft RCC completed. Kollam Project Dn EE
01 Mar 2022 Equilization Tank Raft reinforcement work in progress..., CCT inner wall form work in progress... Kollam Project HD
28 Feb 2022 MBBR I & II Raft reinforcement work in progress..., CCT wall form work in progress..., Chlorine room wall outside plastering work started Kollam Project HD
26 Feb 2022 Sludge Thickner & Pre-treatment unit Earth excavation in progress..., CCT 1st lift wall inside form work in progress..., MBBR - 1& 2 Raft reinforcement work in progress. Kollam Project HD
25 Feb 2022 Sludge Thickner - Earth excavation in progress..., CCT 1st lift wall inside form work in progress..., MBBR - 1& 2 Raft reinforcement work in progress...,MBBR - 3 Raft reinforcement work completed .... Kollam Project HD
24 Feb 2022 second lot epoxy coated steel arrived at site on 20/2/2022 and reinforcement works of all components started and in good progress. Raft RCC of MBBR no.3, Equilization tank sump portion is proposed on 25.02.2022 Kollam Project HD
23 Feb 2022 Sludge Thickener - Earth excavation in progress..., CCT 1st lift wall inside form work in progress..., MBBR - III & II Raft reinforcement work in progress..., Chlorine room block work in progress... Kollam Project HD