| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Feb 2022 | CCT-Form work & reinforcement work going on.....Clarifier 2-1st lift wall form work & reinforcement work going on......MBBR 3 reinforcement for raft progressing....Pre-Treatment unit earth work going on......Sludge Thickner earth excavation started | Kollam Project HD | |
| 21 Feb 2022 | Equilization tank pcc completed...clarifier 2 1st lift wall form work & reinforcement work in progress...CCT 1st lift wall form work & reinforcement work are progressing ..MBBR 3 Reinforcement for Raft work in progress ..Pre-treatment unit earth excavation work continues | Kollam Project HD | |
| 21 Feb 2022 | Equilization tank pcc completed...clarifier 2 1st lift wall form work & reinforcement work in progress...CCT 1st lift wall form work & reinforcement work are progressing ..MBBR 3 Reinforcement for Raft work in progress ..Pre-treatment unit earth excavation work continuous | Kollam Project HD | |
| 19 Feb 2022 | For Equilization tank , pcc for the slop bed is completed .remaining flat portion will be done 19.2.2022.MBBR 3 reinforcement for Raft is going on ..chlorine contact tank form work for side wall is progressing .Pre-treatment unit earth excavation progressing | Kollam Project HD | |
| 18 Feb 2022 | Equilization tank slop portion pcc work in progress...CCT 1st lift wall inside form work in progress ..Clarifier 2 1st lift wall inside form work in progress ..MBBR 3 Raft reinforcement work | Kollam Project HD | |
| 17 Feb 2022 | Equalization Tank part earth excavation work in progress..., CCT inside wall shuttering work for 1st lift in progress...., Chlorine Room wall block work in progress..., Primary Unit earth excavation work in progress..., MBBR-IV wall curing work going on...., Clarifier-II wall shuttering work in progress... | Kollam Project HD | |
| 16 Feb 2022 | Equilization Tank balance earth leveling work in progress.... CCT 1st lift wall inside form work in progress ...Primary treatment units excavation works in progress. | Kollam Project HD | |
| 15 Feb 2022 | works of Equalization tank PCC - part completed on 14.02.2022 , leveling of balance part in progress. Chlorine room block work in progress.. CCT inner shuttering in started ... Primary treatment units excavation works in progress..MBBR no.1 PCC works completed. | Kollam Project HD | |
| 13 Feb 2022 | MBBR no. 1 PCC works completed | Kollam Project Dn EE | |
| 11 Feb 2022 | Equilization tank part pcc work completed… work for mbbr no. 1 excavation completed and leveling in progress.. MBBR IV wall curing work progress ..Clarifier 2 wall shutter work in progress.. | Kollam Project HD |