| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 27 Jan 2022 | work for secondary clarifier no.1 RCC work in progress…excavation of equilization tank in progress | Kollam Project HD | |
| 26 Jan 2022 | work for secondary clarifier no.1 RCC work planned on 27.01.2022 . Part bill ( CC II ) ( total amount of Rs.16352431 ) released to the contractor on 25.01.2022. | Kollam Project HD | |
| 26 Jan 2022 | Equilization tank earth excavation works in progress...Clarifier no 2...raft rcc completed.. curing progress...MBBR III ...dewatering and reinforcement work ..Clarifier no 1..raft form work progress... | Kollam Project HD | |
| 24 Jan 2022 | Clarifier no 2...raft rcc completed.....Curing work progress....equilization tank earth excavation works in progress.... | Kollam Project HD | |
| 24 Jan 2022 | Clarifier no 2...raft rcc completed....MBBR III dewatering and raft reinforcement works in progress...MBBR IV inside wall form work in progress...equilization tank earth excavation works in progress... | Kollam Project HD | |
| 22 Jan 2022 | Raft secondary Clarifier rcc work in progress...equilization tank earth excavation works in progress...MBBR IV inside wall form work in progress...MBBR III dewatering and raft reinforcement works in progress... | Kollam Project HD | |
| 19 Jan 2022 | MBBR IV ...inside wall form work progress...Clarifier no 2..inside and outside wall starter form work..equilization tank earth excavation work progress..MBBR II and III PCC completed..Chlorine room slab curing work..MBBR III dewatering progress... | Kollam Project HD | |
| 18 Jan 2022 | MBBR IV..form work progress...Chlorine room ...slab RCC...completed Clarifier no 1..center shaft raft RCC..completed...equilization tank earth excavation works in progress... | Kollam Project HD | |
| 13 Jan 2022 | MBBR IV .. inside form work in progress...Clarifier no 2..centre shaft reinforcement work...Clarifier no 1...reinforcement works in progress...MBBR II..PCC works in progress.. Chlorine room slab reinforcement works in progress..equilization tank earth excavation started... | Kollam Project HD | |
| 12 Jan 2022 | CCT ..wall reinforcement works in progress...Chlorine room slab shuttering and beam reinforcement works in progress...Clarifier no 2 getting ready for concrete...Clarifier no 1..reinforcement works in progress...MBBR IV wall reinforcement progress...MBBR II.. earth excavation progress... Compound wall plastering.. | Kollam Project HD |