Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Dec 2022 72.50 % work completed..,Septage pump house roof slab form work in progress.., Sledge thickner walkway form work in progress..., Sludge holding tank side wall final lift form work in progress..., Pre-treatment unit grit chamber beam form work in progress. Kollam Project HD
30 Nov 2022 72.50 % work completed.., Sledge thickner walkway formwork in progress..., Sludge holding tank side wall final lift formwork in progress..., Pre-treatment unit grit chamber beam formwork in progress. Kollam Project HD
29 Nov 2022 Sledge thickner walk way form work in progress...,Sludge holding tank side side wall final lift form work in progress...,Pre-treatment unit grit chamber beam form work in progress. Kollam Project HD
28 Nov 2022 Sledge thickner walk way form work in progress...,Sludge holding tank side side wall final lift form work in progress. Kollam Project HD
27 Nov 2022 Sledge shed rcc work completed..,sludge holding tank side wall final lift form work in progress Kollam Project HD
26 Nov 2022 Sludge shed roof slab rcc work in progress..,Sledge thickner walk way form work in progress...,Sludge holding tank side side wall final lift form work in progress...,Sludge thickner walk way form work in progress. Kollam Project HD
25 Nov 2022 Sludge thickner walk way form work in progress...,Sludge shed roof slab reinforcement work in progress Kollam Project HD
24 Nov 2022 Sludge shed...Roof slab reinforcement work in progress...Holding tank ...reinforcement and form work in progress...Thickener...walkway and final lift form work in progress...Pretreatment unit ...beam form work in progress... Kollam Project HD
23 Nov 2022 pretreatment unit... beam form work in progress...Holding tank... reinforcement work in progress... Sludge shed... Roof slab reinforcement work in progress...sludge thickener ...walkway and final lift form work in progress... Kollam Project HD
22 Nov 2022 Sludge shed...roof slab reinforcement work in progress.. Sludge thickener...walkway and final lift form work in progress...Mbbr 2.. walkway and final lift form work in progress...pre-treatment unit ....beam form work in progress.. Holding tank ....reinforcement work in progress... Kollam Project HD