| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending....Centrifuge building staircase reinforcement work in progress...MBBR 3&4 connecting channel shuttering work in progress...Admin building pile chipping work in progress..Sec. Clarifier 1 launder wall shuttering work in progress... | Kollam Project HD | |
| 11 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending....Sludge shed beam plastering work in progress...Admin building pile chipping work in progress... | Kollam Project HD | |
| 10 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Transformer room column Rcc work completed...Equalization tank staircase column Rcc work completed...MBBR 3&4 connecting channel second lift Rcc work completed..Centrifuge building staircase reinforcement work in progress.. | Kollam Project HD | |
| 09 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..CCT final lift and walkway Rcc work in progress...and RCC completed.. Sludge thickner mechanism erection work in progress...Transformer room column works in progress...Sludge thickener erection works started... | Kollam Project HD | |
| 08 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..CCT final lift and walkway Rcc work in progress...and RCC completed.. | Kollam Project HD | |
| 07 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..CCT final lift and walkway Rcc work in progress...and RCC completed.. | Kollam Project HD | |
| 06 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..CCT final lift and walkway Rcc work in progress...and RCC completed.. | Kollam Project HD | |
| 05 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..CCT final lift and walkway Rcc work in progress...and RCC completed.. | Kollam Project HD | |
| 04 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Transformer room footing RCC work in progress...Pre-treatment unit screens (fine&coarse) erection work in progress...Centrifuge building staircase footing RCC work in progress...Equilization tank staircase footing RCC work in progress... | Kollam Project HD | |
| 03 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Sec. Clarifier 1 launder slab sidewall shuttering work in progress....Sec.Clarifier 2 walkway shuttering and reinforcement work in progress... | Kollam Project HD |