| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Backfilling work in progress between clarifier 2 and manhole chamber ...Clarifier 2 final lift sidewall shuttering work in progress... Reinforcement work in MBBR 3 in progress... | Kollam Project HD | |
| 30 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Clarifier 2 final lift sidewall shuttering work in progress... Manhole curing work in progress... | Kollam Project HD | |
| 29 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Clarifier 2 final lift sidewall shuttering work in progress...Inlet chamber walkway RCC completed...Curing progress...Manhole chamber sidewall deshuttering work in progress.... | Kollam Project HD | |
| 28 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Clarifier 2 sidewall final lift shuttering work in progress...Inlet chamber walkway ready for concrete...Inlet chamber walkway RCC in progress... | Kollam Project HD | |
| 27 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Inlet chamber walkway shuttering and reinforcement work in progress...Clarifier 1 sidewall deshuttering work in progress...Clarifier 2 sidewall final lift shuttering work in progress... | Kollam Project HD | |
| 26 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Manhole chamber sidewall first lift rcc work in progress...Inlet chamber walkway shuttering and reinforcement work in progress... | Kollam Project HD | |
| 25 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Manhole chamber sidewall shuttering work in progress...Inlet chamber walkway reinforcement work in progress...Cable trench backfilling work in progress... | Kollam Project HD | |
| 24 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Sec-Clarifier 2 launder slab RCC completed...curing progress...Inlet chamber walkway reinforcement work in progress...manhole chamber sidewall shuttering work in progress... | Kollam Project HD | |
| 23 Jul 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Inlet chamber walkway shuttering and reinforcement work in progress...Sec.Clarifier 1 center shaft reinforcement work in progress...Clarifier 1 walkway shuttering work in progress. | Kollam Project HD | |
| 22 Jul 2023 | Civil works - 14 components completed out of 35 , Electro - Mechanical items - 22 out 32 supplied at site , Errection works not started yet..Inlet chamber walkway shuttering and reinforcement work in progress...Sec.Clarifier 1 center shaft reinforcement work in progress...Clarifier 1 walkway shuttering work in progress... | Kollam Project HD |