| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet.Clarifier 1 walkway reinforcement and shuttering work in progress...MBBR 1&2 Connecting channel reinforcement and shuttering work in progress... | Kollam Project HD | |
| 09 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet.Clarifier 1 walkway reinforcement work in progress..Sludge manhole chamber final lift ready for concrete..Sludge pump house plastering work in progress...MBBR 1&2 Connecting channel reinforcement work in progress... | Kollam Project HD | |
| 08 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet.Clarifier 1 walkway reinforcement work in progress..Transformer room Excavation work in progress..MBBR 1&2 connecting channel reinforcement work in progress... | Kollam Project HD | |
| 07 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet.MBBR 1&2 connecting channel reinforcement work in progress...Clarifier 1 walkway reinforcement work in progress...Inlet chamber side wall grinding work in progress...Sludge pump house plastering work in progress... | Kollam Project HD | |
| 06 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Septage plant room plastering work in progress...Clarifier 1 walkway shuttering work in progress.. | Kollam Project HD | |
| 05 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..MBBR 3 wall grinding work in progress...MBBR 1&2 connecting channel reinforcement work in progress....MBBR 3 outlet chamber shuttering work in progress..Clarifier 1 launder slab deshuttering work in progress | Kollam Project HD | |
| 04 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Sludge manhole chamber sidewall shuttering work in progress..MBBR 3 outlet chamber shuttering work in progress...Clarifier 1 walkway shuttering work in progress... | Kollam Project HD | |
| 03 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Manhole chamber final lift reinforcement work in progress....MBBR 1&2 connecting channel shuttering work in progress...Clarifier 2 walkway reinforcement work in progress... | Kollam Project HD | |
| 02 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Backfilling work in progress between clarifier 2 and manhole chamber ...Clarifier 2 final lift sidewall shuttering work in progress... Reinforcement work in MBBR 3 in progress.. | Kollam Project HD | |
| 01 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet..Backfilling work in progress between clarifier 2 and manhole chamber ...Clarifier 2 final lift sidewall shuttering work in progress... Reinforcement work in MBBR 3 in progress.. | Kollam Project HD |