Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Admin building pile cap PCC work completed....Equalization tank staircase reinforcement and shuttering work in progress..Sec. Clarifier 1 launder wall shuttering work in progress.... Kollam Project HD
21 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Sec. Clarifier 1 &CCT connecting channel reinforcement work in progress...Admin building Earth leveling work in progress...MBBR 3 &4 connecting channel shuttering work in progress....Anti vibration pad fixing (Air blower) work in progress... Kollam Project HD
20 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Centrifuge feed pump foundation reinforcement work in progress...Equalization tank staircase reinforcement work in progress....Backfilling in progress ( Transformer room foundation)... Kollam Project HD
19 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Conveyor fixing work in progress...Anti vibration pad fixing (Air blower) work in progress....Sec. Clarifier 1 & CCT connecting channel reinforcement work in progress.... Kollam Project HD
18 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Equalization tank staircase reinforcement work in progress...Sec. Clarifier 1 & CCT connecting channel reinforcement work in progress... Kollam Project HD
17 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Equalization tank staircase reinforcement work in progress...Sec. Clarifier 1 & CCT connecting channel reinforcement work in progress... Kollam Project HD
16 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Centrifuge feed pump foundation RCC completed..MBBR 3&4 connecting channel reinforcement and shuttering work in progress..Centrifuge building staircase RCC completed.. Kollam Project HD
15 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...MBBR 3 -4 Connecting channel reinforcement work in progress....Sec. Clarifier 1 launder slab wall shuttering work in progress...Centrifuge feed pump foundation reinforcement work in progress.... Kollam Project HD
14 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Centrifuge building staircase reinforcement and shuttering work in progress...Equalization tank staircase shuttering work in progress...Sludge shed plastering work in progress...Admin building pile chipping work in progress...MBBR 3 -4 Connecting channel reinforcement work in progress... Kollam Project HD
13 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending....Centrifuge building staircase reinforcement work in progress...MBBR 3&4 connecting channel shuttering work in progress...Admin building pile chipping work in progress..Filtrate cum thickened sludge pump house - Pump Foundation PCC in progress... Kollam Project HD