| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Admin building column reinforcement work in progress...MCC Room block work in progress...Sludge Thickner mechanism erection work in progress...Cable laying work in progress..... | Kollam Project HD | |
| 11 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Equalization tank Hand Railing work in progress..Sludge Thickener mechanism erection work in progress...Cable trench excavation& laying work in progress.. | Kollam Project HD | |
| 10 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Aerator building excavation work started..Sludge Thickener mechanism erection work in progress...Cable trench excavation work in progress... | Kollam Project HD | |
| 09 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..MCC Room block work in progress....Cable trench excavation work in progress....Sludge pump house earth levelling work in progress....Transformer room plinth beam reinforcement work in progress | Kollam Project HD | |
| 08 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Transformer room plinth beam PCC work in progress....Admin building column reinforcement work in progress.... | Kollam Project HD | |
| 07 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Transformer room plinth beam earth levelling for PCC work in progress...Filtration unit foundation shuttering work in progress...Admin building column reinforcement work in progress... | Kollam Project HD | |
| 06 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Centrifuge building staircase foundation reinforcement and shuttering work in progress...Sludge Thickner mechanism erection work in progress...MCC Room block work in progress...Filtration unit footing reinforcement work in progress... | Kollam Project HD | |
| 05 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Filtration unit PCC work in progress...Sludge Thickener mechanism erection work in progress....Admin building column setout work in progress... | Kollam Project HD | |
| 04 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Air Blower building plastering work in progress....Sludge thickener mechanism erection work in progress.... | Kollam Project HD | |
| 03 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Air Blower building plastering work in progress....Sludge thickener mechanism erection work in progress.... | Kollam Project HD |